10.06.2020

Liquidated damages and penalty clauses: the last word on Honey Bees

The Supreme Court’s judgment in 127 Hobson Street Limited & Anor v Honey Bees Preschool Limited & Anor [2020] NZSC 53 confirms the test for determining when a clause in a contract designed to secure performance will be an unenforceable penalty.  The decision rejects the previous law that a liquidated damages clause must be based on a genuine pre-estimate of loss, or risk being struck down as a penalty.  Parties wanting to challenge a clause as penal must show it is out of all proportion to, or exorbitant when compared with, the interest being protected.  This is a high bar.

The facts

127 Hobson Street Limited (127 Hobson) agreed to lease building space to Honey Bees Preschool Limited (Honey Bees).  Because the childcare centre would create significant pressure on lift access, 127 Hobson agreed to install a second lift in the building (the Collateral Deed).  The Collateral Deed contained a clause requiring 127 Hobson to indemnify Honey Bees for all Honey Bees’ obligations under the lease (including rent and outgoings) if the lift was not installed on time.  The lift was not installed on time.  Honey Bees used the clause to claim an indemnity from 127 Hobson for its rent and outgoings.  127 Hobson challenged the clause, arguing it was unenforceable as a penalty.

The Honey Bees decision

Until now, the New Zealand position on penalty clauses reflected the British position: to be enforceable, liquidated damages clauses needed to be a genuine pre-estimate of damages.  The UK Supreme Court recently overturned this concept,[1] noting that a party’s legitimate interests might extend beyond compensation for loss.  It proposed a new test, which asked whether the clause in question protects a legitimate performance interest; and whether the penalty imposed is out of all proportion to the interest being protected. 

 The Honey Bees decision provides a definitive ruling on the position in New Zealand.  The key findings are as follows:

  • A clause which imposes a consequence if the contract is breached will be unenforceable if the consequence is “out of all proportion” to the legitimate interest the other party has in the contractual obligation being performed.
  • A clause is not a penalty if the consequences it imposes are designed to protect the party’s interests in the obligations under the contract being performed. These are legitimate interests.
  • Determining whether a clause is an unenforceable penalty requires an objective analysis of the contract, its terms and circumstances, and the broader commercial context.
  • A conventional assessment of contractual damages may not adequately capture a party’s legitimate interests: these may extend beyond the loss caused by the contractual obligations not being performed.
  • Deterring a breach of contract can be a legitimate objective, although punishment is not legitimate.
  • The parties’ bargaining power, their commercial sophistication, and whether they had legal advice will be taken into account in assessing a liquidated damages clause.

The Supreme Court found that by requiring the installation of the second lift, Honey Bees was protecting its legitimate business interests to ensure orderly access throughout the building.  Honey Bees did not take advantage of an unequal bargaining position.  The Court found that the consequences of the indemnity clause being triggered were not out of all proportion to the legitimate interests Honey Bees had secured.  The indemnity clause was not a penalty and was upheld by the Court.

Our comment

Liquidated damages are frequently used in construction contracts, to secure the completion of the works by the Due Date for Practical Completion.  In view of the Honeybees decision, liquidated damages clauses agreed by commercial parties will become increasingly more difficult to challenge.  It will be necessary to show that the level of liquidated damages is wholly disproportionate to the Principal’s interest in securing timely performance of the obligations under a construction contract. 

Parties should consider the specific interests which are being protected through a liquidated damages clause (or any other clause that might be considered punitive).  Parties should be able to articulate a clear basis for the clause being included in the contract, together with a justification for the amount of any “penalty”. 

If you have any questions about the issues raised by this judgment or the law on penalty clauses, please get in touch with our Construction Team, or your usual contact at Hesketh Henry.

 

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

[1] Cavendish Square Holdings BC v Makdessi; ParkingEye Ltd v Beavis [2015] UKSC 67, [2016] AC 1172, (Cavendish).

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Library BW
Director Residential Address Protection – Bill is passed into law
Last week, the Companies (Address Information) Amendment Act 2025 (the Act) was enacted.  The Act permits directors who have serious concerns about the disclosure of their residential address to elec...
24.11.2025 Posted in Corporate & Commercial
Business Succession Planning – Shareholder Agreements What have you and your co-investors agreed?
A successful exit from a business can be, and often is, affected by the steps you take when setting up the business. Although there are various business structures that can be used in New Zealand, by ...
06.11.2025 Posted in Corporate & Commercial & Private Wealth
Post-Employment Obligations – Worth the Paper They Are Written On?
“Gone are the days … when an employee could confidently sign up to a restraint and then breach it in the bold expectation that ‘those things are not worth the paper they are written on’”.[1]...
22.10.2025 Posted in Employment
Proportionate Liability – the Next Evolution?
The current line of authorities establishing the ability for building owners to be able to claim in negligence for the cost of rectifying defects can be traced to the Court of Appeal’s (COA) judgmen...
17.10.2025 Posted in Construction & Insurance
New Zealand’s Resource Management Reform: Understanding the 2025 Amendment Act’s Transformative Changes to Fines and Insurance Coverage
Introduction The resource management landscape in New Zealand has undergone a seismic shift with the recent passage of the Resource Management (Consenting and Other System Changes) Amendment Act 2025,...
10.09.2025 Posted in Regulatory
vecteezy a man in a suit is holding his finger to his lips   Extended fade cropped
Pay secrecy no more – what you need to know about the most recent employment law change
Conversations about what employees earn are no longer prohibited or required to be shrouded in secrecy. The Employment Relations (Employee Remuneration Disclosure) Amendment Bill came into force on 27...
29.08.2025 Posted in Employment
HH Pg  Wave alternative
The America’s Cup Partnership and the Deed Of Gift: Navigating Legal Tensions
The newly released protocol (Protocol) for the 38th America’s Cup (AC38) marks another chapter in the evolution of the world’s oldest international sporting trophy.  While the Protocol introduces...
26.08.2025 Posted in Disputes & Private Wealth & Trade and Transport
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.