13.12.2013

Ridgecrest New Zealand Ltd v IAG New Zealand Ltd [2013] 3 NZLR 618

Ridgecrest owned a commercial building in Christchurch that was insured by IAG NZ. The policy provided repair / replacement cover under the following alternative provisions:

C1:  This insurance will pay the amount of loss or damage or the estimated cost of restoring your Business Assets as nearly as possible to the same condition they were in immediately before the loss or damage happened using current materials and methods.

C2:  Where Replacement cover has been agreed by us and specified in the Schedule and following loss or damage you restore or replace the lost or damaged Business Assets this insurance will pay

  • For Buildings
  • Where repairable, the cost of restoration of damage to the same condition when new,

or

(ii)  If unable to be repaired because of such damage, the cost of replacement by an equivalent building which meets your requirements at any site provided we shall not pay more than the cost of replacement at the Site stated in the Schedule.

The building suffered damage in each of four Canterbury earthquakes during the period of insurance and was ultimately demolished.  It was repairable after the first two earthquakes on 4 September and 26 December 2010, and remedial works had begun when the third struck on 22 February 2011.  The parties disagreed as to whether the building became irreparable at that point but agreed that it was beyond repair after the fourth earthquake on 11 June 2011.

Ridgecrest made separate claims after each earthquake.  The issue was whether it was entitled to be paid the aggregate value of the damage caused by each earthquake (or ‘happening’).  IAG NZ took the position that, once the building was irreparable, it was only required to pay the cost of replacement up to the limit of indemnity.  The policy contemplated multiple claims during the period of insurance but did not specifically address what would happen when this occurred.

The High Court found in favour of IAG NZ on the basis that the policy had been “frustrated” by the destruction of the building, which rendered IAG NZ’s obligation to effect repairs impossible.  The High Court implied a term that discharged IAG NZ from paying for losses arising from the earlier earthquakes.  In its judgment, the High Court declined to apply the doctrine of merger – ie where there is unrepaired damage followed by total loss, the insured can only recover the total loss.  The doctrine exists in marine insurance but the High Court was not convinced that it had any wider application either in this specific case or as a matter of general law.

On appeal, the Court of Appeal reached the same conclusion but by an entirely different route.  It drew a distinction between C1 and C2.  If the claims had been made under C1, Ridgecrest might have been entitled to payment for the estimated repair costs up to the limit of indemnity after each earthquake.  Whereas, under C2, IAG NZ’s liability was limited to the cost of the uncompleted repairs actually carried out and the cost of replacing the building up to the limit of indemnity.

In the absence of a clear statement, the Court of Appeal determined that the claims were made under C2.  The judgment goes to some lengths to justify this conclusion and to “shut the door” on Ridgecrest subsequently changing the basis of its claims to bring them under C1.  The Court observed that the statement of claim did not reference C1 nor allege that the claims were made under C1.  Further, it would have defied commercial common sense for Ridgecrest to make a claim for repairs on an old-for-old basis under C1 when new-for-old cover was available under C2.  The Court also noted that after the first two earthquakes, IAG NZ assumed responsibility for arranging repairs and met the cost of these.  While this was not strictly in accordance with C2, it was indicative of a claim under C2.  Had the claims been made under C1, the Court would have expected Ridgecrest to demand payment of its estimated repair costs, rather than acquiescing to IAG NZ’s repair arrangements.

The Court of Appeal’s reasoning in relation to C2 is somewhat forced.   For example, the pleadings appear to have been silent as to which clause applied.  What is essentially a pleading point could be “corrected” if Ridgecrest was permitted to amend its statement of claim.  The basis of the Court’s judgment means that the decision has limited value as a precedent: were an insured to claim under C1, the outcome may well be different.

The Court of Appeal’s conclusion meant it did not need to consider the doctrines of merger or frustration.  However, it indicated in obiter that it would not have upheld the High Court’s conclusion on frustration, which was based on an implied term, as it was contrary to the express terms of the policy and was not necessary to give the policy business efficacy.

Ridgecrest has been granted leave for a further appeal to the Supreme Court.  This will allow the parties to advance all previous arguments, including those on the doctrines of merger and frustration.  We will provide a further update once that decision is released.

Back to Summary Table

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Fern forest NZ
Bioenergy in New Zealand: Fuels for the Future?
The energy transition from combustion fuels to low carbon alternatives is viewed as critical in the race to cut global CO2 emissions and reach climate targets.  We look at some of the opportunities p...
14.11.2023 Posted in Business Advice & Climate Change & Forestry
Will Wide BW
A well drafted will is a craft
The New Zealand do-it-yourself “DIY” attitude and way of life is not limited to home improvements, but sometimes also extends to wills.  Recently we had a DIY $5.99 fill in the blanks will acros...
07.11.2023 Posted in Private Wealth
rsz large pillars
Health and Safety: The Consequences of Dishonesty
Siddhartha Gautama said that lies are like huge, gaudy vessels, the rafters of which are rotten and worm-eaten, and that those who embark in them are fated to be shipwrecked.  Two remarkable health a...
03.11.2023 Posted in Employment & Health & Safety
Properly sequencing your Construction Adjudications: Henry Construction Projects Ltd v Alu-Fix (UK) Ltd
According to the UK’s Technology and Construction Court (TCC) (in Henry Construction Projects Ltd v Alu-Fix (UK) Ltd [2023] EWHC 2010) valid payment claims must be paid before the underlying merits ...
30.10.2023 Posted in Construction & Disputes
Key change to rules on distribution of surplus assets under the new Incorporated Societies Act 2022
On 5 October 2023, the new Incorporated Societies Act 2022 (2022 Act) came fully into force, replacing the Incorporated Societies Act 1908 (1908 Act). One of the key requirements under the 2022 Act is...
18.10.2023 Posted in Business Advice
Construction Framework Wide BW
Major milestone passed – NZS3910:2023 expected in time to fill Christmas stockings
As the most widely adopted standard form construction contract in NZ, NZS 3910 was more than ready for updated conditions given the changes in the industry since its last review in 2013.  After almos...
09.10.2023 Posted in Construction
Time is money – availability provisions in employment agreements and the requirement to compensate
What happens when an availability provision is non-compliant because it does not allow for compensation, but the employee is not “required” to work additional hours?  Can the employee still be sa...
21.09.2023 Posted in Business Advice & Employment
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.