10.07.2020

Design life in the spotlight

Blackpool Borough Council v Volkerfitzpatrick [2020] EWHC 1523 (TCC)

In 2009, Blackpool Borough Council (Principal), as principal, contracted with Volkerfitzpatrick Ltd (Contractor), as head contractor, to design and build a tram depot at Starr Gate, Blackpool in the UK.  As is frequently also the case in New Zealand, the depot building was in close proximity to the sea air and was exposed to harsh environmental conditions.  

The Depot was completed in 2011 and brought into operation in 2012.  Since its completion, the Depot suffered from premature corrosion.  The Principal claimed that significant parts of the building did not meet their intended design life of 50 years and were not suitable for the harsh coastal marine environment.   It claimed £6.7m from the Contractor for the remedial works of the affected parts of the building, which was largely galvanized steel cold formed components; and the Contractor in turn sought to pass on any liability it may have to consultants (as third parties to the litigation) involved in the project.

The main issue in dispute was whether the parts of the defective construction work fell within the term “building structure”, which had a minimum “design life” obligation of 50 years as specified in the “Functional Procurement Specification”, as opposed to the default minimum design life obligation of 20 years as outlined in section 2.3.5 of the “Works Information”.  Both of these were contract documents.

Meaning of “design life”

As there was no definition of “design life” in the contract, the Court referred to other industry standards for guidance, and in particular 1.5.2.8 of BS EN 1990:2002  ‘Design Working Life’, which provided that it is an “assumed period for which a structure or part of it is to be used for its intended purpose with anticipated maintenance but without major repair being necessary.  The Court considered it plausible that a structure ought not to need major repairs during its design life but implausible for the structure to be maintenance-free during its design life.  A distinction is therefore required to be drawn between anticipated maintenance and major repair, which is a question of degree and fact in each case.

The Judge accepted the Contractor’s position that item 1.9 of the consulting engineer’s design log provided the clearest guidance for the minimum design life allocated to the different structures of the building.  The purpose of the design log was to “clarify technical design assumptions and intent” and was provided to accompany the tender and the Contractor’s ‘Works Information’ in the beginning.  For this reason, and given that the parties had effectively treated the design log as a contractual document by their conduct, the Court was satisfied it should be given contractual effect.

Contractual “design life” requirements

The consulting engineer had provided in the design log that the structural frame and rail support structures should have a minimum design life of 50 years and the components that form the external shell should have a minimum design life of 25 years.  Further, these were strict obligations given the specific environmental condition that the depot was located in.

There was also no express definition of what was meant by either the structural frame or the external shell, nevertheless, the Court looked at the role of each component to deduce their contractual design life.  The judge concluded that simply because it is not clear, it cannot be said to fall within the default 20 years design life as stated in the Works Information.  He also looked at the specifics of each component such as minimum galvanized coating thickness and the extent to which the component needs to withstand the harsh environment to deduce whether they formed part of the structural frame or the external shell.  As a result, the Court was able to rule that the cold formed components should have a design life of 25 years rather than 50 years.

Compliance with “design life” requirements

The Court then determined whether each applicable component had met its contractual design life requirement.  This was assessed by weighing up expert evidence on the extent of corrosion of the components with the Principal’s alleged failure to maintain them where maintenance was necessary.

Overall, the Contractor admitted that components other than the cold-formed components did not meet its design life requirements.  The Principal had carried out standard maintenance, as was specified in the contract.  By adhering to the standard specified in the contract, the Principal’s maintenance practice did not have a significant contribution to the resulting corrosion of the components.  In reaching this conclusion, given the particular location of the tram depot, the Court held that it was the Contractor’s obligation to agree on non-standard or unduly onerous maintenance requirements with the Principal. As the Contractor failed to comply with this obligation, it was held that the Principal should be placed in the position it would have been in had the Contractor complied.

Damages awarded

Despite claiming only £6.7m in remedial costs, the Principal was only awarded £1.1m.

The Court did not award any damages for the cold-formed components as they required limited replacement or repairs and were not inadequate for their 25 year design life.  This meant damages were limited to the remedial costs necessary for those components that did not meet the required design life (comprising the roof components, wall cladding panels, roof overhang soffit panels, wave form cladding panels, tram doors and certain other items). The Court relied on experts’ evidence to determine the extent of remedy required for the components to conclude on a total remedial cost of £1.1m for the defective components.

The decision illustrates the value of taking the time (and seeking advice) to ensure contractual terms are sufficiently clear and that all necessary documents form part of a construction contract.  It also emphasizes the importance of design life requirements in construction where the site is exposed to harsh sea environments, which is frequently the case in New Zealand, as it was in Blackpool.

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Flooded car
Flooding due to overland flow paths and damaged drainage
Persistent heavy rainfall across the country often results in damage to property due to flooding caused by overland flow paths and defective drainage.  But who is responsible for the cost of the dama...
17.06.2025 Posted in Climate Change & Property
Understanding Indirect Privacy Notification: What you need to know
The Privacy Amendment Bill (the Bill), if passed into law, will require agencies to notify individuals when their personal information is collected from a source other than the individual themselves, ...
16.06.2025 Posted in Corporate & Commercial & Employment
iStock  Succession Plan medium
Family Ties: Intra-Family Succession and Exit Planning
As the second instalment in a series of articles looking at the generational wealth transition and its impacts on business succession in New Zealand, Ben Hickson (partner, Corporate & Commercial...
16.06.2025 Posted in Corporate & Commercial & Private Wealth
Employment law at a glance – June 2025
If you are anything like us, you will be shocked to realise that we are halfway into 2025. As time has been marching on, so too have employment law developments – and there have certainly been quite...
05.06.2025 Posted in Employment
HH Pg  Forrest uncropped
ETS Update: Climate Change Commission recommends minor tweaks to ETS Settings
Last month, He Pou a Rangi Climate Change Commission (the Commission) released its annual advice to the Government on the Emissions Trading Scheme (ETS) settings for the period 2026 to 2030 (Advice)....
HS Scrabble Med Crop Vignette
Health and safety learnings for landowners following latest Whakaari decision
The leasing and subleasing of land, buildings and infrastructure is commonplace in New Zealand business and commerce, but what happens when something goes wrong? Do landowners have health and safety o...
08.05.2025 Posted in Health & Safety
Navigating Settlor Intentions in Trust Restructures – Legler v Formannoij [2024] NZSC 173
In Legler v Formannoij the surviving widow Marina Formannoij, was forced to navigate the complexities of two trusts that were part of her late husband Ricco Legler’s estate plan: the Kaahu Trust (wh...
08.05.2025 Posted in Private Wealth
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.