14.09.2023

Disruption claims: Are your project records up to date?

Disruption can be hard to pinpoint.  It is one of those features that you know when you see it and most parties have likely felt it on a construction project.  However, being able to make a claim for the effects of disruption and prove that claim to enable financial recovery can be another matter altogether.

What is disruption?

Disruption is, essentially, the loss of productivity felt by a contractor caused by unanticipated interruptions to the progress of the works.  It is defined in the SCL Delay and Disruption Protocol (2nd Edition February 2017 at [43]) as:

A disturbance, hindrance or interruption to a Contractor’s normal working methods, resulting in lower efficiency.  Disruption claims relate to a loss of productivity in the execution of particular activities.  Because of the disruption, these work activities are not able to be carried out as efficiently as reasonably planned (or as possible). 

At its heart, a disruption claim is a claim made by a contractor for the additional costs arising from the loss of efficiency or productivity (being lost work efficiency (labour and utilisation of plant) and an increase in direct time spent on those same tasks) – when compared with what had initially been planned.

Disruption claims involve a forensic programming and quantity surveying examination and are claims that are made after the fact once the productivity impact has occurred. 

Disruption and delay are separate

A claim for disruption does not depend on delay to the critical path (although, that may also be the case).  These are two separate concepts, despite the common reference to claims being for ‘delay and disruption’.  It is very much a separate analysis, and distinct from delay. 

A delay impacts completion of the works as a whole (if it is a critical delay) leading to a claim for an extension of time and potentially prolongation costs, whilst disruption is the loss of productivity to a specific work activity.  Disruption may cause delay, but it can also arise because of sub-critical delay or from events that do not cause delay at all.  It is therefore conceptually different to a prolongation claim.  Indeed, disruption can, for example, occur and be a symptom of acceleration. 

The effect of disruption may not be visible or immediately felt when compared with a traditional delaying event that would give rise to an extension of time.  Sometimes it will be obvious that efficiency has dropped off.  However, depending on the nature of the project, it may not be until weekly or even monthly progress or financial reports are prepared that any loss of productivity will be observed.  Given this, to repeat an adage, it is critical that project records are kept up to date.

How do you establish relief? 

There are four steps to establish a disruption claim:

  1. Identify the relevant event(s) or cause(s) of the disruption;
  1. Ascertain whether the contract gives the contractor an entitlement to recovery for disruption either under a specific clause or by way of damages for breach of contract;
  1. Prove that the event(s) caused disruption; and
  1. Quantify the cost of the disruption.

Identify the event(s) 

The first step is to identify that there was a disruption of activities and what caused that disruption.  This may seem obvious, but it is necessary to set out the disruption event(s) as a foundation step, to then be able to identify what consequences flow from each event.

Does the contract allow recovery? 

Second, disruption must be recoverable under the contract.   Most standard form contracts (eg NZS3910:2013) do not expressly address recovery for disruption.  Instead, they may give an entitlement to claim some of the events that could lead to recovery in the form of loss and expense or damages.  Unless dealt with separately in special conditions, disruption claims generally proceed as claims seeking damages for breach of contract.  In considering entitlement, care should be taken to check the special conditions as to whether there is:

  • Any specific notification requirement(s);
  • A loss and expense clause which may bar recovery of costs associated with disruption;
  • Any entitlement under the variations clause (including as part of valuation of variations) which could prevent or reduce the recovery of disruption costs as a separate claim; and
  • Any compensation right(s) as a result of an acceleration instruction, as a claim for disruption may not be available where it has been caused by acceleration measures.

Prove causation

The next element is causation.  Ideally, the claim will describe each individual event, and what the result of it was, in as much detail as possible.  This involves:

  • Identification and analysis of each of the exact operations (labour and plant) claimed to have been disrupted (rather than just a bare statement that the works have been disrupted); and
  • Using the above to establish a narrative link showing how the disruptive event caused disruption to certain activities.

The list of matters that may cause disruption can be open ended, but examples could include the combined or cumulative effect of multiple variations, late instructions and/or the unavailability of work faces.  Usually, it will be a combination or accumulation of causes that leads to disruption.

Just as a principal may cause the contractor to be disrupted, there are a range of factors in which a contractor themselves can impede productivity or efficiency (or which a principal can say are the responsibility of a subcontractor), which need to be considered in a disruption claim.  Allowance should be made for matters that are within the contractor’s responsibility such as a lack of skilled labour, lack of QA processes followed or inadequate site supervision.

Quantify the claim 

This may involve assessment by expert programmers and quantity surveyors to ascertain the extent and impact of the disruption event and the costs recoverable.  Evidence will be required to demonstrate:

  • The cause (events) of the disruption;
  • The impacted activity and progress of work that was disrupted;
  • The impacted period of work; and
  • The additional labour and equipment expended on the disrupted activity.

Project records are key

The most important consideration, underpinning both causation and quantification, is the evidence (documents) that is required to establish relief in a disruption claim.  It can be clear to everyone on site that the works are not progressing efficiently, but proving that a loss has been caused, and quantifying that loss is a separate matter, which can be challenging.

The importance of having evidentiary documentation was discussed in the leading case, Walter Lilly v MacKay & Anor ([2012] EWHC 1773 (TCC) at [486(c)])The Court said that there is no set way to prove the elements and that it is open to contractors to prove them with whatever evidence will satisfy the tribunal to the requisite standard of proof.  Therefore, the closer the evidence is to the coal face, the more convincing it is likely to be.

In Van Oord & Anor v Allseas UK Ltd ([2015] EWHC 3074 (TCC)) the Court noted that contemporaneous documents are a useful starting point when trying to work out what was happening on site at any given time, and what the relevant individuals thought were the important events on site during the works.  Van Oord emphasises that a lack of contemporaneous documents can be detrimental to a claim.

Record keeping is key to proving a disruption claim.  It is important to keep project documentation to support what happened on site, including, for example, emails, letters, minutes of meetings, progress reports, site diaries, personal notebooks, allocation sheets, site photos, day work sheets / time records and time lapse recordings.  

Parties should try to take the time to ensure that their project records are comprehensive and up to date, in the event that a disruption claim arises.  The worst position for a claiming party to end up in, is being unable to prove its case on the balance of probabilities. 

If you have any questions about possible disruption claims, or you have any questions regarding matters of construction law, please get in touch with our Construction Team, or your usual contact at Hesketh Henry.

 

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

 

 

 

Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Mediation wide BW
Employment Law’s Dispute Resolution Process – Employment Relations Authority and Employment Court
In our last article, we introduced the dispute resolution process in the employment jurisdiction by discussing mediation – specifically, what mediation is and what to expect. This article discusses ...
17.04.2025 Posted in Employment
You’ve Been Served: Navigating the Use of Statutory Demands
An Introduction to Statutory Demands: A statutory demand is a legal document that is issued by a creditor (Creditor) to a debtor company (Debtor) demanding payment of a debt that is due and owing.  T...
15.04.2025 Posted in Insolvency and Restructuring
iStock  Succession Plan medium
Passing the Torch: Priming your Family Business for a Succession
As the first in a series of articles looking at the generational wealth transition and its impacts on business succession in New Zealand, Ben Hickson (partner, Corporate & Commercial) and John Kir...
07.04.2025 Posted in Corporate & Commercial & Private Wealth
Deciding to Wind Up? Observations on winding-up a trust from a recent High Court case
A trust can be a hassle and expensive to maintain.  So, it is not unusual for clients to reflect on whether a trust should be maintained. When settlors, Bert and Diana Queenin, decided to wind up the...
24.03.2025 Posted in Private Wealth
Mediation wide BW
Employment Law’s Dispute Resolution Process – Mediation
Navigating the dispute resolution process in the employment jurisdiction can be tricky. This article aims to spell out the key considerations for those involved in or contemplating mediation, which is...
24.03.2025 Posted in Employment
empty wallet finance concept
Amendment to the Crimes Act 1961: Intentionally not paying employees their wages now deemed theft
An amendment to the Crimes Act 1961 (Crimes Act) – the Crimes (Theft by Employer) Amendment Bill has been passed by Parliament and received Royal assent. It is now an enforceable provision of th...
14.03.2025 Posted in Employment
Time’s Up: Late Redelivery and the Assessment of Damages in Hapag Lloyd AG v Skyros Maritime Corporation and Hapag Lloyd AG v Agios Minas Shipping Company
The English Commercial Court gave an instructive judgment on the assessment of damages in Hapag Lloyd AG v Skyros Maritime Corporation and Hapag Lloyd AG v Agios Minas Shipping Company; an appeal brou...