14.09.2023

Disruption claims: Are your project records up to date?

Disruption can be hard to pinpoint.  It is one of those features that you know when you see it and most parties have likely felt it on a construction project.  However, being able to make a claim for the effects of disruption and prove that claim to enable financial recovery can be another matter altogether.

What is disruption?

Disruption is, essentially, the loss of productivity felt by a contractor caused by unanticipated interruptions to the progress of the works.  It is defined in the SCL Delay and Disruption Protocol (2nd Edition February 2017 at [43]) as:

A disturbance, hindrance or interruption to a Contractor’s normal working methods, resulting in lower efficiency.  Disruption claims relate to a loss of productivity in the execution of particular activities.  Because of the disruption, these work activities are not able to be carried out as efficiently as reasonably planned (or as possible). 

At its heart, a disruption claim is a claim made by a contractor for the additional costs arising from the loss of efficiency or productivity (being lost work efficiency (labour and utilisation of plant) and an increase in direct time spent on those same tasks) – when compared with what had initially been planned.

Disruption claims involve a forensic programming and quantity surveying examination and are claims that are made after the fact once the productivity impact has occurred. 

Disruption and delay are separate

A claim for disruption does not depend on delay to the critical path (although, that may also be the case).  These are two separate concepts, despite the common reference to claims being for ‘delay and disruption’.  It is very much a separate analysis, and distinct from delay. 

A delay impacts completion of the works as a whole (if it is a critical delay) leading to a claim for an extension of time and potentially prolongation costs, whilst disruption is the loss of productivity to a specific work activity.  Disruption may cause delay, but it can also arise because of sub-critical delay or from events that do not cause delay at all.  It is therefore conceptually different to a prolongation claim.  Indeed, disruption can, for example, occur and be a symptom of acceleration. 

The effect of disruption may not be visible or immediately felt when compared with a traditional delaying event that would give rise to an extension of time.  Sometimes it will be obvious that efficiency has dropped off.  However, depending on the nature of the project, it may not be until weekly or even monthly progress or financial reports are prepared that any loss of productivity will be observed.  Given this, to repeat an adage, it is critical that project records are kept up to date.

How do you establish relief? 

There are four steps to establish a disruption claim:

  1. Identify the relevant event(s) or cause(s) of the disruption;
  1. Ascertain whether the contract gives the contractor an entitlement to recovery for disruption either under a specific clause or by way of damages for breach of contract;
  1. Prove that the event(s) caused disruption; and
  1. Quantify the cost of the disruption.

Identify the event(s) 

The first step is to identify that there was a disruption of activities and what caused that disruption.  This may seem obvious, but it is necessary to set out the disruption event(s) as a foundation step, to then be able to identify what consequences flow from each event.

Does the contract allow recovery? 

Second, disruption must be recoverable under the contract.   Most standard form contracts (eg NZS3910:2013) do not expressly address recovery for disruption.  Instead, they may give an entitlement to claim some of the events that could lead to recovery in the form of loss and expense or damages.  Unless dealt with separately in special conditions, disruption claims generally proceed as claims seeking damages for breach of contract.  In considering entitlement, care should be taken to check the special conditions as to whether there is:

  • Any specific notification requirement(s);
  • A loss and expense clause which may bar recovery of costs associated with disruption;
  • Any entitlement under the variations clause (including as part of valuation of variations) which could prevent or reduce the recovery of disruption costs as a separate claim; and
  • Any compensation right(s) as a result of an acceleration instruction, as a claim for disruption may not be available where it has been caused by acceleration measures.

Prove causation

The next element is causation.  Ideally, the claim will describe each individual event, and what the result of it was, in as much detail as possible.  This involves:

  • Identification and analysis of each of the exact operations (labour and plant) claimed to have been disrupted (rather than just a bare statement that the works have been disrupted); and
  • Using the above to establish a narrative link showing how the disruptive event caused disruption to certain activities.

The list of matters that may cause disruption can be open ended, but examples could include the combined or cumulative effect of multiple variations, late instructions and/or the unavailability of work faces.  Usually, it will be a combination or accumulation of causes that leads to disruption.

Just as a principal may cause the contractor to be disrupted, there are a range of factors in which a contractor themselves can impede productivity or efficiency (or which a principal can say are the responsibility of a subcontractor), which need to be considered in a disruption claim.  Allowance should be made for matters that are within the contractor’s responsibility such as a lack of skilled labour, lack of QA processes followed or inadequate site supervision.

Quantify the claim 

This may involve assessment by expert programmers and quantity surveyors to ascertain the extent and impact of the disruption event and the costs recoverable.  Evidence will be required to demonstrate:

  • The cause (events) of the disruption;
  • The impacted activity and progress of work that was disrupted;
  • The impacted period of work; and
  • The additional labour and equipment expended on the disrupted activity.

Project records are key

The most important consideration, underpinning both causation and quantification, is the evidence (documents) that is required to establish relief in a disruption claim.  It can be clear to everyone on site that the works are not progressing efficiently, but proving that a loss has been caused, and quantifying that loss is a separate matter, which can be challenging.

The importance of having evidentiary documentation was discussed in the leading case, Walter Lilly v MacKay & Anor ([2012] EWHC 1773 (TCC) at [486(c)])The Court said that there is no set way to prove the elements and that it is open to contractors to prove them with whatever evidence will satisfy the tribunal to the requisite standard of proof.  Therefore, the closer the evidence is to the coal face, the more convincing it is likely to be.

In Van Oord & Anor v Allseas UK Ltd ([2015] EWHC 3074 (TCC)) the Court noted that contemporaneous documents are a useful starting point when trying to work out what was happening on site at any given time, and what the relevant individuals thought were the important events on site during the works.  Van Oord emphasises that a lack of contemporaneous documents can be detrimental to a claim.

Record keeping is key to proving a disruption claim.  It is important to keep project documentation to support what happened on site, including, for example, emails, letters, minutes of meetings, progress reports, site diaries, personal notebooks, allocation sheets, site photos, day work sheets / time records and time lapse recordings.  

Parties should try to take the time to ensure that their project records are comprehensive and up to date, in the event that a disruption claim arises.  The worst position for a claiming party to end up in, is being unable to prove its case on the balance of probabilities. 

If you have any questions about possible disruption claims, or you have any questions regarding matters of construction law, please get in touch with our Construction Team, or your usual contact at Hesketh Henry.

 

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

 

 

 

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Privacy Commissioner to consult on Privacy Rules for Biometric Information
With the increasing use of facial recognition technology (FRT), retinal scans, and voice recognition by an array of different agencies, privacy concerns about its collection and use are set to be form...
24.11.2023 Posted in Business Advice
Fern forest NZ
Bioenergy in New Zealand: Fuels for the Future?
The energy transition from combustion fuels to low carbon alternatives is viewed as critical in the race to cut global CO2 emissions and reach climate targets.  We look at some of the opportunities p...
14.11.2023 Posted in Business Advice & Climate Change & Forestry
Will Wide BW
A well drafted will is a craft
The New Zealand do-it-yourself “DIY” attitude and way of life is not limited to home improvements, but sometimes also extends to wills.  Recently we had a DIY $5.99 fill in the blanks will acros...
07.11.2023 Posted in Private Wealth
rsz large pillars
Health and Safety: The Consequences of Dishonesty
Siddhartha Gautama said that lies are like huge, gaudy vessels, the rafters of which are rotten and worm-eaten, and that those who embark in them are fated to be shipwrecked.  Two remarkable health a...
03.11.2023 Posted in Employment & Health & Safety
Properly sequencing your Construction Adjudications: Henry Construction Projects Ltd v Alu-Fix (UK) Ltd
According to the UK’s Technology and Construction Court (TCC) (in Henry Construction Projects Ltd v Alu-Fix (UK) Ltd [2023] EWHC 2010) valid payment claims must be paid before the underlying merits ...
30.10.2023 Posted in Construction & Disputes
Key change to rules on distribution of surplus assets under the new Incorporated Societies Act 2022
On 5 October 2023, the new Incorporated Societies Act 2022 (2022 Act) came fully into force, replacing the Incorporated Societies Act 1908 (1908 Act). One of the key requirements under the 2022 Act is...
18.10.2023 Posted in Business Advice
Construction Framework Wide BW
Major milestone passed – NZS3910:2023 expected in time to fill Christmas stockings
As the most widely adopted standard form construction contract in NZ, NZS 3910 was more than ready for updated conditions given the changes in the industry since its last review in 2013.  After almos...
09.10.2023 Posted in Construction
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.