18.06.2018

Ebert Construction Limited v Sanson [2017] NZCA 239

The Court of Appeal allowed an appeal by Ebert Construction Limited (Ebert) which challenged the ability of the liquidators of a developer company to claw back payments made by a financier under a direct payment agreement.  The Court held that the payments made by the financier were under a direct obligation to a builder, and were therefore not payments by the insolvent company, and were therefore not subject to the insolvent transactions regime.  The form of direct payment agreements or tripartite agreements will be important, particularly in voidable transaction cases.

Background

In October 2005 Takapuna Procurement Limited (TPL) entered into a construction contract with Ebert to construct the 134-unit Shoalhaven Apartments complex at Takapuna for approximately $32,500,000.  TPL arranged finance with BOS International (Australia) Limited (BOSI) through a Senior Facility Agreement and Strategic Nominees Limited (Strategic) through a Junior Facility Agreement.

The direct agreement

Ebert, BOSI and Strategic entered into a “direct agreement” in relation to the project.

Direct agreements generally provide for a contractor’s progress payments to be paid directly by the financier.  They typically provide a financier with “step in rights” if a developer defaults on their obligations.  The direct agreement in this case included the following relevant features:

  1. BOSI was required to pay Ebert progress payments due under the construction contract provided a) BOSI had received an approval payment certificate for the amount to be paid and b) Ebert was not in default of its obligations under the construction contract.
  2. TPL gave an irrevocable authority for these payments to be made by BOSI direct to Ebert.
  3. BOSI and Strategic could only terminate TPL’s finance facilities if they first paid duly approved progress payments to Ebert.
  4. Neither BOSI nor Strategic had any liability or obligation to Ebert other than as provided in the direct agreement. TPL remained “primarily liable” for all obligations under the construction contract.  However, BOSI had the right to step in and complete the project if TPL defaulted on its obligations under the construction contract.
  5. A default by TPL under its loan facility agreement did not discharge BOSI from its obligations to Ebert under the direct agreement. This provision was described as unusual in direct agreements.

Completion of the project and insolvency

The apartments were completed in April 2008.  TPL defaulted on the loan facility with BOSI in July 2008.  In November 2008, TPL and Ebert agreed that the final amount owed to Ebert was $1,603.891.90, which would be paid by way of two cash payments and settlement of the apartment.  TPL issued drawdown notices, and BOSI made payments in accordance with those notices.  An arrangement for the sale of one of the apartments with Ebert as nominated purchaser was also entered into.

TPL was put into liquidation within a few days of these transactions on the application of the Inland Revenue Department.

In the High Court, Associate Judge Doogue held that the two cash payments and the transfer of the apartment were voidable transactions and ordered repayment of $1,603,891.90 plus interest.  Ebert appealed.

A direct liability to pay

The Court of Appeal allowed the appeal.  The key reason was its finding that BOSI had an obligation, as a principal debtor under the direct agreement, to pay Ebert if certain conditions were met.  As a result, the payments were not transactions “by” TPL (as required under s 292 Companies Act 1993), nor did they allow Ebert to receive more than it would otherwise have received in the litigation (as Ebert always had a right to sue BOSI directly).

The Court noted also that the funds paid by BOSI to Ebert would not have been available to any other creditor, and accordingly did not form part of the general resources of the company.  While that is true, it should be noted that the payments made by BOSI to Ebert had the effect of increasing the level of secured debt, and thus reducing the general resources of the company that were available to unsecured creditors.

It is also important to note that the features of the direct agreement which led the Court to its conclusion are not common to all direct agreements.  The Court observed that it is unusual for the financier to have an obligation to pay a contractor in circumstances where the principal has defaulted on the loan agreement.  If a direct agreement provides that direct payments are at the discretion of the financier, the payments may still be vulnerable to claw back in the event of insolvency.

Implications

Contractors presented with a direct agreement need to bear in mind the risk that payments made by a financier could be clawed back by a liquidator in the event of the principal’s insolvency.  To prevent this, the financier must have an obligation (not a discretion) under the direct agreement to pay the contractor that is independent of the direction and will of the principal.


 

Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

HH Pg  Forrest uncropped
ETS Update: Climate Change Commission recommends minor tweaks to ETS Settings
Last month, He Pou a Rangi Climate Change Commission (the Commission) released its annual advice to the Government on the Emissions Trading Scheme (ETS) settings for the period 2026 to 2030 (Advice)....
HS Scrabble Med Crop Vignette
Health and safety learnings for landowners following latest Whakaari decision
The leasing and subleasing of land, buildings and infrastructure is commonplace in New Zealand business and commerce, but what happens when something goes wrong? Do landowners have health and safety o...
08.05.2025 Posted in Health & Safety
Navigating Settlor Intentions in Trust Restructures – Legler v Formannoij [2024] NZSC 173
In Legler v Formannoij the surviving widow Marina Formannoij, was forced to navigate the complexities of two trusts that were part of her late husband Ricco Legler’s estate plan: the Kaahu Trust (wh...
08.05.2025 Posted in Private Wealth
Counting Costs in Arbitration: High Court Affirms Arbitrator’s Discretion on Costs Awards
Construction contracts often require parties to finally resolve disputes through arbitration rather than Court litigation.  One important difference between arbitration and the Courts is that arbitra...
07.05.2025 Posted in Construction & Disputes
Mediation wide BW
Employment Law’s Dispute Resolution Process – Employment Relations Authority and Employment Court
In our last article, we introduced the dispute resolution process in the employment jurisdiction by discussing mediation – specifically, what mediation is and what to expect. This article discusses ...
17.04.2025 Posted in Employment
You’ve Been Served: Navigating the Use of Statutory Demands
An Introduction to Statutory Demands: A statutory demand is a legal document that is issued by a creditor (Creditor) to a debtor company (Debtor) demanding payment of a debt that is due and owing.  T...
15.04.2025 Posted in Insolvency and Restructuring
iStock  Succession Plan medium
Passing the Torch: Priming your Family Business for a Succession
As the first in a series of articles looking at the generational wealth transition and its impacts on business succession in New Zealand, Ben Hickson (partner, Corporate & Commercial) and John Kir...
07.04.2025 Posted in Corporate & Commercial & Private Wealth
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.