19.09.2016

Enforcement of Damages in Adjudication

Does a significant factual dispute preclude summary judgement?

Clark v Central Lakes Homes Limited [2016] NZHC 1694

Introduction

This decision highlights the arbitral distinction in the enforceability of the sums due and rights/obligations under construction contracts, prior to the recent CCA amendments.  In this case, the builder was entitled to enforce an adjudication award of damages only because of a specific contractual right to do so.

Background

The appellant, Clark, contracted Central Lakes Homes Ltd (CLH) to build a residential dwelling on his property in Queenstown.  During construction the relationship between the parties broke down and the construction contract came to an end.  Clark said the contract was terminated mutually, while CLH maintained that Clark had instructed CLH to cease work and refused access to the property.  Clark engaged an alternative builder to complete the works.

The contract stated that the owner will be in breach if he took possession of the building site before completion without the builder’s consent.  In particular, if the owner did not vacate within two working days, the builder would be entitled to terminate the contract immediately, and recover all sums due and owing, together with any damages, costs, expenses, or loss of profit arising out of the determination of the contract.

The dispute was referred to adjudication.  The Adjudicator determined that Clark was liable to pay CLH $62,782.66 for losses and interest under s 48(1)(a) of the Construction Contracts Act 2002 (the Act).

CLH then sought to enforce the adjudicator’s determination in the District Court by applying for summary judgment.  It relied on s 59(2)(a) of the Act, which deems an amount, determined by adjudication (and awarded under s 48(1)(a)) recoverable from the other party as a “debt due”.  The District Court granted CLH’s application for summary judgment, which Clark appealed on the following grounds:

(a)   the determination was made under s 48(1)(b) and therefore cannot be enforced under section 59 by way of summary judgment;
(b)   there are significant factual disputes between the parties, which required determination at a defended hearing, and the matter is therefore not suitable for summary judgment; and
(c)   even if Clark has no defence, the Court in an exercise of its residual discretion should not enter the summary judgment against him.

Was the Adjudicator’s determination validly made under s 48(1)(a)?

At the time this dispute arose, the Act treated differently payments owing under a contract (s48(1)(a)) and rights and obligations of the parties under a contract.  Only determinations made under s 48(1)(a) were able to be enforced (s48(1)(b).  For contracts entered on or after 1 December 2015, that distinction has now been abolished (under the Construction Contracts Act 2015).  However, as this contract was made prior to December 2015, the distinction applied and was the main basis for Clark seeking to overturn summary judgment.

The Court held that the adjudicator’s determination was validly made under s 48(1)(a).

The contract in this case provided the builder with an express right of termination, which, if exercised, caused the owner to be liable for various sums.  These included sums due and owed under the contract, damages, costs, expenses and loss of profit.  Given the express right to such sums, the damages awarded by the adjudicator came within s48(1)(a), meaning the determination was enforceable.

Had there been no contractual right to damages, or other payment, it is likely the determination would have fallen under s48(1)(b) and not been enforceable.

Does a significant factual dispute preclude summary judgment?

There was a significant factual dispute between the parties arising from the events that preceded CLH’s purported termination of the contract.  The Court acknowledged that summary judgment will not normally be appropriate if the case turns on a disputed fact.  Nonetheless, an adjudicator’s determination under s 48(1)(a) is binding and will continue to have full effect unless and until it is set aside by judicial review or, another proceeding is overturned.  This follows the ‘pay now argue later’ philosophy of the Act.

Summary judgment of a sum awarded in adjudication under s48(1)(a) may be opposed only where a legitimate jurisdictional question arises (applying Van der Wal Builders and Contractors v Walker HC Auckland  CIV-2010-004-000083, 26 August 2011 which was distinguishable from the present case).  There was no suggestion here that the Adjudicator had been acting outside their jurisdiction.

Residual discretion

This was not an instance in which the Court’s residual discretion to avoid injustice by not upholding an entry of summary judgment was allowed.  The residual discretion is limited and will only be used in exceptional cases.

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

UK Court of Appeal rules that that courts can order parties to engage in ADR: Churchill v Merthyr Tydfil County Borough Council [2023] EWCA Civ 1416
The England and Wales Court of Appeal (EWCA) has held that in certain circumstances, the courts can order parties to engage in alternative dispute resolution (ADR) or stay proceedings to allow the par...
24.07.2024 Posted in Construction & Disputes
Health and Safety Tiles
Updated Guidance: IOD and WorkSafe release ‘Health and Safety Governance – A Good Practice Guide’
While we wait with bated breath for the outcome in the prosecution of former Ports of Auckland CEO, Tony Gibson, officers’ duties are very much at the forefront of everyone’s mind. Section 44 of t...
23.07.2024 Posted in Employment & Health & Safety
Knowing your limits: High Court confirms liability caps in engineering consultancy agreements are consistent with Building Act duties
Design errors in a construction project can result in millions of dollars in loss.  Standard form consultancy agreements typically limit the amount that can be recovered for such errors.  The cap on...
09.07.2024 Posted in Construction & Disputes
glenn carstens peters npxXWgQZQ unsplash
Sender beware – how private are digital workplace conversations?
Following on from the recent Official Information Act request for correspondence between Ministry of Justice employees, employees may be wondering how private their online conversations with colleague...
04.07.2024 Posted in Employment
Concrete pillars impressive
TCC confirms Slip Rule limits in Adjudications
The Technology and Construction Court (TCC) has confirmed the narrow parameters of the ‘slip rule’ in the UK, which allows adjudicators to amend their determination to correct for any clerical or ...
02.07.2024 Posted in Construction & Disputes
Scots rule standard notification clause was condition precedent
In a warning for contractors, a Scottish Court has ruled that a standard form notification clause was a condition precedent to recovering time-related costs (TRCs) (FES Ltd v HFD Construction Group Lt...
01.07.2024 Posted in Construction
rape blossom
Anticipatory Repudiatory Breach and the Date of Default: Ayhan Sezer v Agroinvest
The decision in Ayhan Sezer v Agroinvest [2024] EWHC 479 (Comm) clarifies that where there has been an anticipatory repudiatory breach of contract, the “date of default” is the date of the breach ...
25.06.2024 Posted in Trade and Transport
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.