9.05.2018

Insurance Case Law Update December 2014

In this update, we summarise significant insurance decisions released in the latter part of 2014.

Litigation arising out of the Canterbury earthquakes continues its progress through the levels of appeal.  The Supreme Court’s judgment in Ridgecrest disposed of the doctrine of merger in the context of event-based policies, but identified the “indemnity principle” as a bar to the double counting of damage caused by successive earthquakes.  The application of the indemnity principle was considered further by the Court of Appeal in Wild South/Marriott/Crystal Imports and by the High Court in Morrison.

The Supreme Court’s judgment in Firm PI 1 Ltd v Zurich outlined the principles which apply to contract interpretation in New Zealand.  Disappointingly, the Court did not resolve the controversial question of whether pre-contractual negotiations are able to be used for the interpretation of contracts.  However, the judgment signals a more conservative approach to contract interpretation, in line with that taken in England and Australia.

A more extensive discussion of particular judgments is linked to the case names highlighted in the summary table. For further information on issues raised in this update, please contact the Hesketh Henry insurance law team.

Summary of cases:

 

CaseIssuesDecision / Principle
Ridgecrest v IAG NZ (SC)Entitlement to recover damage caused by successive earthquakesThe doctrine of merger is inconsistent with an event-based policy, where liability is reset after each event.  The indemnity principle caps claims at the replacement value and prevents claims for damage to the same elements of a building.
Firm PI 1 Ltd v Zurich New Zealand (SC)Whether the sum insured was inclusive or exclusive of EQC cover
Contract interpretation
A clause which provided that “Insurer’s liability will be limited to the amount of loss in excess of the Natural Disaster Damage cover” was interpreted in the particular commercial and factual context as meaning the sum insured was inclusive of EQC cover.
University of Canterbury v ICNZ (SC)Requirement to increase the seismic strength of buildingsA territorial authority cannot require a building to be strengthened to a seismic capacity of more than 34% NBS.
Skyward Aviation 2008 Ltd v Tower Insurance (SC)Interpretation of Tower’s Provider House PolicyThe insured, not the insurer, has the right to elect to reinstate the property and to choose between options for reinstatement. If the insured elects to purchase a replacement property, he or she is not obliged to purchase a property which is comparable with the original property when new.
Wild South v QBE
Marriott v Vero
Crystal Imports Ltd v Lloyd’s (CA)
Entitlement to recover damage caused by successive earthquakes
Automatic reinstatement of cover
When a property is destroyed
Application of average
Where damage occurs in successive earthquakes, recovery is limited to the repair of cumulative damage and any repairs undertaken before further damage occurred.
Interpretation of automatic reinstatement clauses.  Cover reinstates after each successive earthquake.  Notice of cancellation can be given prospectively; cover and liability for premium remain in place until the notice date.
Destruction depends on the facts of each case; whether repairs are physically feasible is not the only consideration.
The measure of value when applying average is the elected measure of loss (indemnity value or reinstatement value, as the case may be).
Avonside Holdings Ltd v Southern Response (CA)Assessment of hypothetical costs of rebuildRight to acquire another property capped at the cost of rebuilding the insured property on the existing site.  Hypothetical cost of rebuild should include contingencies and professional fees.
New Zealand Fire Service Commission v Insurance Brokers Association Of New Zealand Incorporated [2014] NZCA 179, [2014] 3 NZLR 541Calculation of fire service levies under section 48, Fire Service Act 1975 on “split tier” and “multi insured composite” fire insurance policiesLevies based on “amount for which the property is insured” could be a reference to indemnity value or the sum insured.  For “split tier” policies:
1. If settlement is upon a basis no more favourable to the insured than indemnity value, and specifies a sum insured lower than its indemnity value, the levy is to be computed on the sum insured.
2. If a policy provides cover for indemnity value and contains a capped sum insured, the levy is computed on the sum insured. If the sum insured exceeds the indemnity value of the property, the levy may be calculated on indemnity value.
3. If settlement is limited to value in excess of its indemnity value, no levy is payable on the excess.
For multi insured composite policies, where separate parties insuring separately own property under a single contract of insurance, policy to be viewed as a single contract of insurance and only one levy is payable.
Islington Park Ltd v Ace Insurance Ltd [2014] NZCA 446, (2014) 18 ANZ Insurance Cases 62-038Contract interpretationInterpretation of the contractual measure for a deemed total loss.   Specific to the policy in issue.
Bridgecorp Ltd (in rec & liq) v Lloyd’s [2014] NZCA 571Extra territorial reach of s 9 of the Law Reform Act 1936Claim under s 9, Law Reform Act 1936, against London-based underwriters.   Policy provided for governance by NZ law and exclusive jurisdiction of NZ Courts.  However, debts payable under the policy would be located in England (underwriters’ place of business).  NZ Court lacked jurisdiction to make orders under s 9 requiring the underwriters to pay anyone other than the insured.
Jensen v Rameka (HC)Exemplary damagesClaim under s 9, Law Reform Act 1936, against London-based underwriters.   Policy provided for governance by NZ law and exclusive jurisdiction of NZ Courts.  However, debts payable under the policy would be located in England (underwriters’ place of business).  NZ Court lacked jurisdiction to make orders under s 9 requiring the underwriters to pay anyone other than the insured.
Morrison v Vero (HC)Assessment of damage in multiple earthquake eventsFirst application of indemnity principle to a substantive claim.  Computer model applied to assess damage attributable to each event.  Relief under s 9(1)(b) of the Insurance Law Reform Act for late notification of damage.
Earthquake Commission v ICNZ (HC)Approval of EQC Policy for Increased Flooding VulnerabiityIncreased Flooding Vulnerability and Increased Liquefaction Vulnerability constitute natural disaster damage under the EQC Act.  The EQC’s Policy is consistent with its statutory obligations.  Claimants may challenge EQC decisions by judicial review or in ordinary proceedings.
Kraal v Earthquake Commission [2014] NZHC 919, [2014] 3 NZLR 42, 18 ANZ Insurance Cases 62-015Whether loss of a right to occupy due to a risk of future damage is “physical loss or damage to the property”“Red Zone” property owners unable to occupy home because of risk of rock falls and potential injury.  Owners unsuccessfully sought declarations that loss of possession and use constituted “natural disaster damage” under the EQC Act and “damage” under a private insurance policy.  Inability to occupy is a “loss of the ability to exercise a legal right… not ‘physical loss…to the property’”
Marac Finance Ltd v Vero Liability [2014] NZHC 1974Quantification of loss under Commercial Crime PolicyEndorsement did not alter the meaning of the operative clause of the policy, acted instead as an exclusion clause.  Failure to comply with an arbitration clause will not result in indemnity costs if party has elected to submit to litigation.
Michalik v Earthquake Commission [2014] NZHC 2238Meaning of “indemnity value” in Earthquake Commission Act 1993Indemnity value of a 37 year old retaining wall under the EQC Act is its depreciated replacement value.  Review of meaning of indemnity value under the EQC Act and at common law.
JCS Cost Management v QBE [2014] NZHC 2718Policy responds to claim made, not conduct of insuredPolicy provided cover for civil liability for conduct in connection with a professional business practice.  The claim made against the insured was for conduct which did not fall within the scope of cover.  The policy would not respond, even if the evidence proved that the insured’s conduct was in fact connected to his professional business practice.
MacDonald v Tower Insurance [2014] NZHC 2876Admissibility of evidenceChallenge to admissibility of briefs of evidence prior to trial.  Examples of inadmissible evidence from litigation support agencies/funders and non-experts.
Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry_100x100 1
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Bereavement Leave Confirmed for Miscarriages and Stillbirths 
New Zealand has become the second country in the world to pass legislation that provides bereavement leave for mothers and their partners after a miscarriage or stillbirth.
26.03.2021 Posted in Business Advice & Employment Law
Court of Appeal Overturns Employment Court’s Decision in Tourism Holdings
Tourism Holdings Limited v A Labour Inspector of the Ministry of Business, Innovation and Employment (Tourism Holdings) is the first decision in which the Employment Court considered section 8(2) of the Holidays Act 2003 (Act). The Court of Appeal has recently overturned this decision.
26.03.2021 Posted in Business Advice & Employment Law
Guarantees must be in writing and signed to be enforceable
For a guarantee to be enforceable, the requirements set out in section 27 of the Property Law Act 2007 (Act) must be strictly complied with.  This is what the NZSC held in Brougham v Regan. The key i...
19.03.2021 Posted in Business Advice
UK Supreme Court Delivers Decision on Uber Driver Employment Status
The distinction between employee and independent contractor can be complex, particularly where the nature of the business model blurs the lines of standard employment practices.
16.03.2021 Posted in Business Advice & Employment Law
Holidays Act Overhaul – Taskforce Recommendations
There have been calls for an amendment of the Holidays Act 2003 (Act) for some time.
16.03.2021 Posted in Business Advice & Employment Law
Unwanted Land Covenants and Easements: Seeking a Court Order
The Supreme Court recently considered an application by Synlait Milk to modify a land covenant restricting the burdened land use to farming, grazing and forestry operation to protect the ability of the benefited land owner to develop a quarry.  This article looks at the circumstances in which the courts might give relief to parties in an application to extinguish or modify a covenant or easement.
15.03.2021 Posted in Property Law
New ICC Arbitration Rules 2021 come into force
The revised International Chamber of Commerce (ICC) Arbitration Rules for 2021 (2021 Rules) have now come into force and apply to all ICC arbitrations begun after 1 January 2021.  While the new Rules...
10.03.2021 Posted in Litigation & Dispute Resolution
Send us an enquiry
For expert legal advice, please complete the form below or call us on (09) 375 8700.
  • This field is for validation purposes and should be left unchanged.
-->