9.05.2018

Insurance Case Law Update July 2015

In this update, we summarise significant decisions released in the first half of 2015.

It has been a busy June, with various substantive judgments released by the High Court and Court of Appeal.  Judgments given on preliminary questions are now being tested against findings of fact.  The decision of Kós J in Jarden v Lumley General Insurance (NZ) Ltd highlights the importance of factual evidence and the evidential standards that must be met: “Tea leaves are no substitute for testimony”.

A more extensive discussion of particular judgments is linked to the case names highlighted in the summary table. For further information on issues raised in this update, please contact the Hesketh Henry insurance law team.

Summary of cases:

 

CaseIssuesDecision / Principle
Quake Outcasts v Minister for CER [2015] NZSC 27Lawfulness of Crown offers to purchase uninsured and vacant red zone landDecision to offer to purchase uninsured and vacant land for 50% of its 2007 rateable value was not lawfully made and requires reconsideration.  Crown should not have used its prerogative to create the red zone, but declaration would serve no purpose.
New Zealand Fire Service Commission v Insurance Brokers Association of New Zealand Inc [2015] NZSC 59Calculation of fire service levies under Fire Service Act 1975SC overturned the long standing practice of calculating fire service levies on the indemnity value nominated in the insurance policy, rather than the actual indemnity value.  A composite policy held by eight companies was, on its terms, to be treated as eight contracts, each with a separate indemnity sum on which the levy is payable.  NZFSC agreed the SC’s ruling should not have retroactive effect.
Vero Insurance New Zealand Ltd v Morrison (CA)Assessment of damage in multiple earthquake eventsConsideration of the weight to be given to computer modelling evidence when attributing damage to a particular earthquake event.
Medical Assurance Society of NZ Ltd v East (CA)Payment of repair costs
Meaning of “as new”
If insured elected to restore, insurer’s obligation was to meet actual costs as they were incurred.  “As new” means in accordance with current building consent requirements.
Kraal v EQC [2015] NZCA 13, [2015] 2 NZLR 589, [2015] 18 ANZ Insurance Cases 62-055Whether loss of a right to occupy due to a risk of future damage is “physical loss or damage to the property”“Red Zone” property owners unable to occupy home because of risk of rock falls from neighbouring land, claimed loss of possession and use constituted “natural disaster damage” under the EQC Act and “damage” under a private insurance policy.  CA upheld HC judgment that physical damage to the land or buildings is required.  Deprivation of use does not qualify.  Not a test case by EQC: costs follow the event.
EQC v Whiting [2015] NZCA 144Costs on discontinuanceIf a defendant pays a claim following the issue of proceedings, and the plaintiff discontinues the proceeding, the Court may – at its discretion – award costs to the plaintiff.
Body Corporate 326421 v Auckland Council (HC)Leaky buildings: response of PI policy to claims with multiple causesClaim against main contractor for design and construction defects in the Nautilus apartment tower.  Defects caused by both design and construction errors: cover excluded.
Domenico Trustee Ltd v Tower Insurance Ltd (HC)Insurer’s right of electionInsurer did not elect whether to reinstate or make a payment while negotiations and proceedings were underway.  Delay was not reasonable; law imposed an election to pay the indemnity value subject to any increase for rebuilding costs actually incurred.
Prattley Enterprises Ltd v Vero Insurance New Zealand Ltd (HC)Assessment of damage in multiple earthquake events
Whether settlement based on a misunderstanding can be set aside
Measure of loss under an indemnity policy is the market value of the building, if the insured does not intend to reinstate the building.
No basis to set aside a full and final settlement in circumstances where the insured received independent advice and the insurer acted transparently and in good faith.
Body Corporate 346930 v Argon Construction Ltd [2015] NZHC 129Leaky buildings: liability of Building Industry Authority for regulation of building certifiersBIA does not owe a duty of care in tort to investigate whether a building certifier is acting within the certifier’s scope of authority in circumstances where there is cause to query the certifier’s conduct.  BIA may owe a duty to keep the register of building certifiers up to date.
Houghton v Saunders [2015] NZHC 548Litigation funders and costsThe involvement of litigation funders does not in itself give rise to a right to indemnity costs.  Funders jointly and severally liable for a costs order against the funded party.  A contractual cap on costs in the funding agreement was held to limit the funder’s liability to other parties for their costs.
McCullagh v Underwriters Severally [2015] NZHC 1384Extra territorial reach of s 9 of the Law Reform Act 1936Amounts payable by overseas-based underwriters under policies of insurance are not subject to a charge under s 9.  Charge does not descend when payment is made to an insured within NZ.
AAI Ltd v 92 Lichfield St (in rec and liq) [2015] NZHC 1421Whether a settlement offer was “subject to contract”Offer included a statement that if the settlement was acceptable, a form of discharge would be sent for the appropriate sum.  A dispute arose as to the appropriate sum and the discharge terms.  Parties intended to be bound when the offer was accepted; contract was not dependent on execution of the discharge.  Insured entitled to issue statutory demand for the settlement sum.
Jarden v Lumley General Insurance (NZ) Ltd [2015] NZHC 1427Causation and proofHouse with pre-existing construction defects was damaged in two earthquake events.  Plaintiff has burden of proving cause of damage on the balance of probabilities.
Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry_100x100 1
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Getting the Deal Through: Construction 2019
Partners Nick Gillies, Helen Macfarlane and Christina Bryant are the contributing authors of the New Zealand Chapter of the 2019 edition of “Getting the Deal Through Construction”. Getting...
19.09.2018 Posted in Construction Law
UAE COMPANIES LAW UPDATE
New Zealand businesses looking to establish a foothold in the UAE have many options
10.09.2018 Posted in Trade and Commodities
When You Can’t Have it Your Way
Antares Restaurant Group Limited (which owns and operates Burger King in New Zealand) has received a whopper of a sanction – a ban on the company supporting visa applications until July next year.
4.09.2018 Posted in Employment Law
Getting the Deal Through: Shipping 2019
The Marine team at Hesketh Henry have again contributed to Getting the Deal Through: Shipping 2019.
30.08.2018 Posted in Maritime Law
A Guide to Concurrent Delay
Hesketh Henry was pleased to host the New Zealand Institute of Quantity Surveyors on 14 August 2018, where one of our construction partners, Nick Gillies, presented on concurrent delay.  The same pre...
22.08.2018 Posted in Construction Law
Update – New Zealand’s New Biofouling Standards
New Zealand has introduced a new standard requiring all vessels to have a “clean hull” on arrival in the country after 15  May 2018.[1]  The objective is to minimise the introduction of ...
21.08.2018 Posted in Maritime Law
No Longer Stumped: The Health and Safety at Work Act 2015 Sentencing Guidelines
The High Court at Auckland has released its first and much-awaited decision under the Health and Safety at Work Act 2015 (HSWA).
21.08.2018 Posted in Health & Safety Law
Send us an enquiry
For expert legal advice, please complete the form below or call us on (09) 375 8700.
  • This field is for validation purposes and should be left unchanged.