10.06.2020

Liquidated damages and penalty clauses: the last word on Honey Bees

The Supreme Court’s judgment in 127 Hobson Street Limited & Anor v Honey Bees Preschool Limited & Anor [2020] NZSC 53 confirms the test for determining when a clause in a contract designed to secure performance will be an unenforceable penalty.  The decision rejects the previous law that a liquidated damages clause must be based on a genuine pre-estimate of loss, or risk being struck down as a penalty.  Parties wanting to challenge a clause as penal must show it is out of all proportion to, or exorbitant when compared with, the interest being protected.  This is a high bar.

The facts

127 Hobson Street Limited (127 Hobson) agreed to lease building space to Honey Bees Preschool Limited (Honey Bees).  Because the childcare centre would create significant pressure on lift access, 127 Hobson agreed to install a second lift in the building (the Collateral Deed).  The Collateral Deed contained a clause requiring 127 Hobson to indemnify Honey Bees for all Honey Bees’ obligations under the lease (including rent and outgoings) if the lift was not installed on time.  The lift was not installed on time.  Honey Bees used the clause to claim an indemnity from 127 Hobson for its rent and outgoings.  127 Hobson challenged the clause, arguing it was unenforceable as a penalty.

The Honey Bees decision

Until now, the New Zealand position on penalty clauses reflected the British position: to be enforceable, liquidated damages clauses needed to be a genuine pre-estimate of damages.  The UK Supreme Court recently overturned this concept,[1] noting that a party’s legitimate interests might extend beyond compensation for loss.  It proposed a new test, which asked whether the clause in question protects a legitimate performance interest; and whether the penalty imposed is out of all proportion to the interest being protected. 

 The Honey Bees decision provides a definitive ruling on the position in New Zealand.  The key findings are as follows:

  • A clause which imposes a consequence if the contract is breached will be unenforceable if the consequence is “out of all proportion” to the legitimate interest the other party has in the contractual obligation being performed.
  • A clause is not a penalty if the consequences it imposes are designed to protect the party’s interests in the obligations under the contract being performed. These are legitimate interests.
  • Determining whether a clause is an unenforceable penalty requires an objective analysis of the contract, its terms and circumstances, and the broader commercial context.
  • A conventional assessment of contractual damages may not adequately capture a party’s legitimate interests: these may extend beyond the loss caused by the contractual obligations not being performed.
  • Deterring a breach of contract can be a legitimate objective, although punishment is not legitimate.
  • The parties’ bargaining power, their commercial sophistication, and whether they had legal advice will be taken into account in assessing a liquidated damages clause.

The Supreme Court found that by requiring the installation of the second lift, Honey Bees was protecting its legitimate business interests to ensure orderly access throughout the building.  Honey Bees did not take advantage of an unequal bargaining position.  The Court found that the consequences of the indemnity clause being triggered were not out of all proportion to the legitimate interests Honey Bees had secured.  The indemnity clause was not a penalty and was upheld by the Court.

Our comment

Liquidated damages are frequently used in construction contracts, to secure the completion of the works by the Due Date for Practical Completion.  In view of the Honeybees decision, liquidated damages clauses agreed by commercial parties will become increasingly more difficult to challenge.  It will be necessary to show that the level of liquidated damages is wholly disproportionate to the Principal’s interest in securing timely performance of the obligations under a construction contract. 

Parties should consider the specific interests which are being protected through a liquidated damages clause (or any other clause that might be considered punitive).  Parties should be able to articulate a clear basis for the clause being included in the contract, together with a justification for the amount of any “penalty”. 

If you have any questions about the issues raised by this judgment or the law on penalty clauses, please get in touch with our Construction Team, or your usual contact at Hesketh Henry.

 

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

[1] Cavendish Square Holdings BC v Makdessi; ParkingEye Ltd v Beavis [2015] UKSC 67, [2016] AC 1172, (Cavendish).

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

solar
OIO Spotlight: Solar projects, exempted interests and farmland considerations
As New Zealand renewable energy developments continue to attract interest from global investors, we take a look at some recent approaches of the Overseas Investment Office in assessing consent require...
BCC Trade Credit v Thera Agri Capital: Policyholder Successful Against Credit Insurer in Australian Court of Appeal Decision
When applying for trade credit insurance, a prospective insured will typically provide information on the financing arrangements that will form the basis of cover. Where there is deviation from these ...
05.03.2024 Posted in Insurance & Trade and Transport
iStock
Parker v Magnum Hire: A new era of personal grievance remedies awarded in the Employment Relations Authority?
If you heard a sudden loud noise last week – no it wasn’t a jet plane flying overhead, it was the gasp of employment lawyers across New Zealand when the Employment Relations Authority published it...
26.02.2024 Posted in Employment
employment dictionary website
Banding together: the Court’s new approach to awards for injury to feelings
One of the key remedies available to an employee who has successfully established a personal grievance in the Employment Relations Authority (Authority) or the Employment Court (Court) is compensation...
23.02.2024 Posted in Employment
Trust liability under the Health and Safety at Work Act
WorkSafe New Zealand v RH & JY Trust & ors
21.02.2024 Posted in Health & Safety & Private Wealth
New year, new government, new policies: what’s on the cards for employment law in 2024?
As we have been known to say once or twice (okay, maybe every year!) employment law never stands still. New governments can also spell major change, and this time is no exception. As you will likely h...
14.02.2024 Posted in Business Advice & Employment
Family Hands Paper Dolls Wide BW
Variations of Trust: Court’s Position Confirmed
Last year we published an article titled Variations of Trust: Obtaining the Court’s Blessing on the High Court decision in Re Jury Family Trusts [2022] NZHC 568 (Re Jury). In Re Jury, the High C...
05.02.2024 Posted in Private Wealth
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.