03.07.2015

Medical Assurance Society of NZ Ltd v East [2015] NZCA 250

The Court of Appeal has partly overturned one of the more unexpected decisions from the High Court Earthquake List.[1]  The appeal judgment considers: when the obligation to pay rebuilding costs is incurred; the meaning of “as new”; and the interplay between the policy terms and local authorities in relation to compliant repair methods.

Background

The Easts own a two-storey house built in 2007 with a concrete slab floor and a timber frame on flat land.  The house suffered damage from the Canterbury earthquakes.

Under their policy with MAS, the Easts had the option to either: (1) restore their house, in which case MAS would cover reasonable costs of this on a replacement value basis; or (2) take a cash settlement on an indemnity value basis.  If the Easts elected restoration, the relevant policy provision said:

[MAS] will cover the cost of rebuilding or restoring the dwelling to a condition substantially the same as new, so far as modern materials allow, and including any additional costs which may be necessary to comply with any statutory requirements or Territorial Authority by-laws.  There is no maximum sum insured but the liability of the Society shall not be greater than the reasonable cost to rebuild or restore the dwelling …” [Emphasis added]

The Easts elected to restore their house, and then sought payment up-front from MAS of the estimated costs of this (rather than have MAS pay the actual costs as they were incurred).  The Easts also claimed that underpinning was required in order to restore the house to an “as new” condition, which MAS disputed in favour of a low mobility grout (LMG) method.

Payment of repair costs

In the High Court Whata J had determined that MAS was obliged to pay the Easts the estimated cost of repairing the earthquake damage irrespective of whether liability to incur those costs had been or would ever be incurred.  This was rightly overturned on appeal.

The Court of Appeal held that, if the insured has elected to restore the property, MAS is only obliged to meet the actual restoration costs as they are incurred.  This was consistent with the phrase “will cover”, which is shorthand for “indemnify the insured against”.

In allowing this part of the appeal, the Court returned to orthodox insurance obligations and practices regarding reinstatement cover, which reflect the fact that construction costs are paid incrementally up until completion.  The Court also recognised that an up-front payment on a replacement basis would be tantamount to a cash settlement; yet the policy expressly contemplated that a cash settlement would only be paid on an indemnity basis if the homeowner did not elect to restore the house.

Concerns about the mechanics of an insured seeking payment from their insurer and the “fetter” this might place on the prima facie right to replacement value compensation, did not carry weight in the Court of Appeal.  An insurer’s failure to indemnify actual restoration costs without proper justification would carry “serious legal and reputational costs”, there were no reported cases of this ever occurring, and the absence of any prescribed mechanism in the policy itself was irrelevant.

At the same time, the policy did not provide any mechanism for the insured to account to MAS for any surplus (if the payment was based on an over-estimate) and the High Court decision arguably would have left MAS without any contractual right to recover any surplus.  Further, it would be difficult to prevent the insured from applying the funds to some other purpose or establishing that the claim had been made with a fraudulent intent.

This decision supports a long-standing approach to indemnifying restoration costs and it is likely to have wider application to other policies.  Notwithstanding this, in order to put the matter beyond doubt, insurers should consider whether their policy wordings need revision to make it clear that restoration costs will not be paid until the costs are actually incurred.

“As New” / Building Code

The Court of Appeal upheld that “as new” meant restoring the Easts’ house in accordance with current building consent requirements, rather than those that existed in 2007 when the house was built.  This was the ordinary meaning of the words “as new” and was supported by the reference in the policy wording to compliance with statutory and local requirements.

The standard of repair became relevant after the Easts claimed underpinning was necessary due to the particular ground conditions.  MAS believed this to be “super conservative” and thought the house could instead be re-levelled using LMG or a similar method to the 2007 code requirements.

In the High Court, Whata J concluded that underpinning was necessary in order to meet the current Building Code, but recognised that the Council might reach a different view and approve LMG when granting building consent.  In view of this, leave was reserved to determine quantum issues if that outcome eventuated.  That reservation was unsuccessfully challenged by the Easts in a cross-appeal.  The Court of Appeal said: [2]

“[Whata J] was simply meeting the contingency that, despite his own findings about the appropriate engineering solution, the Council may nevertheless approve the solution favoured by MAS.  As the consenting authority, the Council has the ultimate word on this issue.  It was appropriate for the Judge to reserve leave to settle quantum if the Easts’ claim ultimately fell for measure on a different basis from that proposed”.

Quantum – exaggerated claims

During the trial the plaintiffs’ QS conceded “significant errors” in his estimate, which resulted in a grossly exaggerated claim.  This did not go unnoticed by the Court of Appeal.  Considerable indulgence was granted to the plaintiffs’ QS to reconsider his costing, and with leave reserved to determine quantum if necessary.

Back to Summary Table

[1] East v Medical Assurance Society [2014] NZHC 3399

[2] Local authority building consent decisions may be re-heard by way of Ministry Determination.

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Fern forest NZ
Bioenergy in New Zealand: Fuels for the Future?
The energy transition from combustion fuels to low carbon alternatives is viewed as critical in the race to cut global CO2 emissions and reach climate targets.  We look at some of the opportunities p...
14.11.2023 Posted in Business Advice & Climate Change & Forestry
Will Wide BW
A well drafted will is a craft
The New Zealand do-it-yourself “DIY” attitude and way of life is not limited to home improvements, but sometimes also extends to wills.  Recently we had a DIY $5.99 fill in the blanks will acros...
07.11.2023 Posted in Private Wealth
rsz large pillars
Health and Safety: The Consequences of Dishonesty
Siddhartha Gautama said that lies are like huge, gaudy vessels, the rafters of which are rotten and worm-eaten, and that those who embark in them are fated to be shipwrecked.  Two remarkable health a...
03.11.2023 Posted in Employment & Health & Safety
Properly sequencing your Construction Adjudications: Henry Construction Projects Ltd v Alu-Fix (UK) Ltd
According to the UK’s Technology and Construction Court (TCC) (in Henry Construction Projects Ltd v Alu-Fix (UK) Ltd [2023] EWHC 2010) valid payment claims must be paid before the underlying merits ...
30.10.2023 Posted in Construction & Disputes
Key change to rules on distribution of surplus assets under the new Incorporated Societies Act 2022
On 5 October 2023, the new Incorporated Societies Act 2022 (2022 Act) came fully into force, replacing the Incorporated Societies Act 1908 (1908 Act). One of the key requirements under the 2022 Act is...
18.10.2023 Posted in Business Advice
Construction Framework Wide BW
Major milestone passed – NZS3910:2023 expected in time to fill Christmas stockings
As the most widely adopted standard form construction contract in NZ, NZS 3910 was more than ready for updated conditions given the changes in the industry since its last review in 2013.  After almos...
09.10.2023 Posted in Construction
Time is money – availability provisions in employment agreements and the requirement to compensate
What happens when an availability provision is non-compliant because it does not allow for compensation, but the employee is not “required” to work additional hours?  Can the employee still be sa...
21.09.2023 Posted in Business Advice & Employment
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.