03.12.2014

Morrison v Vero Insurance New Zealand Ltd [2014] NZHC 2344

This case grappled with the issue of how to apportion damage between multiple insured events – specifically the Canterbury earthquakes.  The Court had to evaluate the efficacy of modelling in the absence of full direct evidence of the damage caused by each event.

Background

The plaintiff owned a commercial building that was indemnified by the defendant.  The total sum insured was $3,482,000 per event, with cover reinstating at the end of each event.  The object of an indemnity payment under the policy was to return the plaintiff to its position prior to the event of loss (ie on an old-for-old basis).

The plaintiff claimed there were five earthquake events causing loss – on 4 September and 26 December 2010 and on 22 February, 6 April and 13 June 2011.  The plaintiff estimated the total amount payable for damage caused by these events at $13,100,000.  In support of this the plaintiff employed modelling to identify the five events of loss and estimate the extent of damage from each.  In simple terms, the model measured the ground shaking intensity of the specified earthquakes and their corresponding relative impact on the resilience of the building.

The defendant believed that only the September and February earthquakes caused damage, amounting to circa $3,985,000 applying the per event cap.  It rejected the modelling as unreliable and contended that most, if not all, major elements were beyond repair after February 2011 so that subsequent damage was not material or claimable.

Modelling and the apportionment of damage

The Court acknowledged that modelling involves value judgments and, in this particular case, some of the defendant’s criticisms had merit, including the inability of the model to incorporate the effects of liquefaction.  However, these were not sufficient to render the plaintiff’s model wholly unreliable.  It was helpful for the purpose of understanding the relative impact of the earthquakes – as one input in the allocation of damage.  In other words, the Court endorsed the use of modelling as a tool, but stressed that an overall judgment was still needed based on both the qualitative and quantitative evidence as to the likely apportionment of damage and repair across the events.

Here the Court did not accept that the December and April earthquakes were likely to have caused any damage or that the modelling estimate for the September earthquake was accurate.  To this extent the model was rejected, but the scope of damage estimated by the plaintiff for the February and June events was generally accepted.  The parties were invited to quantify the loss themselves based on these findings.

Material damage / constructive loss

The Court did not accept the defendant’s argument that the building was effectively destroyed after the February earthquake, such that no additional sum is payable for further damage caused by the June earthquake.

Applying Ridgecrest[1], the Court acknowledged that an insurer cannot be required to pay more than the cost to replace a damaged item.  However, on these particular facts, the June repair scope submitted by the plaintiff related only to items that were not included for replacement in the February earthquake.  There was also evidence (including the modelling) that the June earthquake had caused material damage (any other conclusion was thought to be “highly improbable”).  The Court also seems to have been influenced by the defendant’s implied election not to give notice preventing the reinstatement of cover after the earlier and much more significant February event.

Late notice

The plaintiff failed to inform the defendant of damage after the December, April and June earthquakes, despite the policy requiring immediate notification.

For the first two of these events, the absence of notice was irrelevant as the Court had already found that no material damage was caused, although s 9(1)(b) of the Insurance Law Reform Act 1977 would not have availed the plaintiff even if they had.  That section provides that time limits on giving notice are only binding if the insurer was so prejudiced that it would be inequitable not to enforce the notice provision.  Here the lack of notice for December and April deprived the defendant of an opportunity to inspect the damage or stop reinstatement.

By contrast, for the June earthquake, the Court was willing to apply s 9(1)(b).  Unlike December and April, this was the last of the earthquakes on which a claim was based and the second largest in order of magnitude.  As a result, it was not easily missed and there was an opportunity for the defendant to observe the state of the building afterwards (albeit some time later).

Expert witnesses

 Somewhat unusually, the Court was critical of the caucusing between experts in that it was not as successful as it ought to have been.  The Court stressed the need for actual and apparent independence of experts, early and meaningful discussions well in advance of trial, and constant professionalism (after one unfortunate incident).

Back to Summary Table

[1] Ridgecrest NZ Ltd v IAG New Zealand Ltd [2014] NZSC 129, click here for our review of the decision

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Team Hands in small
Cartel conduct: Do not pass “GO”, go directly to jail
Until 8 April 2021, cartel conduct was punishable only by civil penalty in New Zealand.  In R v Kumar [2024] NZHC 3955 the High Court imposed the first criminal convictions and sentences for cartel c...
06.03.2025 Posted in Construction & Disputes
Employment
2025 Insights: Proposed Legislative Changes and Employment Team Update
Team update and proposed legislative change – hello from the Hesketh Henry Employment Law Team 2025. Click here
20.02.2025
photo  dbe
When Sweet Turns Sour: The Costly Consequences of Contamination
The New Zealand Sugar Company (NZSC), trading as Chelsea Sugar, recently found itself in hot water after being fined nearly $149,500 by the District Court due to a prosecution brought by the Ministry ...
19.02.2025 Posted in Insurance & Trade and Transport
Mind your business: What happens when an employer uses an employee’s personal information?
A recent decision by the Human Rights Review Tribunal (the Tribunal) provides a noteworthy reminder of the importance of privacy rights and obligations in the workplace.  In BMN v Stonewood Group Lim...
14.02.2025 Posted in Employment
Construction Framework Wide BW
Public consultation on NZS 3916:2025 and NZS 3917:2025
Public consultation on the draft DZ 3916 Conditions of contract for building and civil engineering – Design and construct and DZ 3917 Conditions of contract for building and civil engineering – F...
13.02.2025 Posted in Construction
Court of Appeal rules Gloriavale’s challenges to BNZ decision to close its account are not seriously arguable
Background BNZ made the decision to close the accounts of 16 entities associated with the Gloriavale Christian Community following a decision by senior management that this action was appropriate give...
07.02.2025 Posted in Disputes & Insurance
Milford sound
Government unveils ‘Invest New Zealand’ agency to position NZ as premier FDI destination
Yesterday, the Prime Minister Rt Hon Christopher Luxon announced the Government’s plan to establish a new foreign investment agency, as part of his ‘State of the Nation’ speech in Auckland.  We...
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.