03.12.2014

Morrison v Vero Insurance New Zealand Ltd [2014] NZHC 2344

This case grappled with the issue of how to apportion damage between multiple insured events – specifically the Canterbury earthquakes.  The Court had to evaluate the efficacy of modelling in the absence of full direct evidence of the damage caused by each event.

Background

The plaintiff owned a commercial building that was indemnified by the defendant.  The total sum insured was $3,482,000 per event, with cover reinstating at the end of each event.  The object of an indemnity payment under the policy was to return the plaintiff to its position prior to the event of loss (ie on an old-for-old basis).

The plaintiff claimed there were five earthquake events causing loss – on 4 September and 26 December 2010 and on 22 February, 6 April and 13 June 2011.  The plaintiff estimated the total amount payable for damage caused by these events at $13,100,000.  In support of this the plaintiff employed modelling to identify the five events of loss and estimate the extent of damage from each.  In simple terms, the model measured the ground shaking intensity of the specified earthquakes and their corresponding relative impact on the resilience of the building.

The defendant believed that only the September and February earthquakes caused damage, amounting to circa $3,985,000 applying the per event cap.  It rejected the modelling as unreliable and contended that most, if not all, major elements were beyond repair after February 2011 so that subsequent damage was not material or claimable.

Modelling and the apportionment of damage

The Court acknowledged that modelling involves value judgments and, in this particular case, some of the defendant’s criticisms had merit, including the inability of the model to incorporate the effects of liquefaction.  However, these were not sufficient to render the plaintiff’s model wholly unreliable.  It was helpful for the purpose of understanding the relative impact of the earthquakes – as one input in the allocation of damage.  In other words, the Court endorsed the use of modelling as a tool, but stressed that an overall judgment was still needed based on both the qualitative and quantitative evidence as to the likely apportionment of damage and repair across the events.

Here the Court did not accept that the December and April earthquakes were likely to have caused any damage or that the modelling estimate for the September earthquake was accurate.  To this extent the model was rejected, but the scope of damage estimated by the plaintiff for the February and June events was generally accepted.  The parties were invited to quantify the loss themselves based on these findings.

Material damage / constructive loss

The Court did not accept the defendant’s argument that the building was effectively destroyed after the February earthquake, such that no additional sum is payable for further damage caused by the June earthquake.

Applying Ridgecrest[1], the Court acknowledged that an insurer cannot be required to pay more than the cost to replace a damaged item.  However, on these particular facts, the June repair scope submitted by the plaintiff related only to items that were not included for replacement in the February earthquake.  There was also evidence (including the modelling) that the June earthquake had caused material damage (any other conclusion was thought to be “highly improbable”).  The Court also seems to have been influenced by the defendant’s implied election not to give notice preventing the reinstatement of cover after the earlier and much more significant February event.

Late notice

The plaintiff failed to inform the defendant of damage after the December, April and June earthquakes, despite the policy requiring immediate notification.

For the first two of these events, the absence of notice was irrelevant as the Court had already found that no material damage was caused, although s 9(1)(b) of the Insurance Law Reform Act 1977 would not have availed the plaintiff even if they had.  That section provides that time limits on giving notice are only binding if the insurer was so prejudiced that it would be inequitable not to enforce the notice provision.  Here the lack of notice for December and April deprived the defendant of an opportunity to inspect the damage or stop reinstatement.

By contrast, for the June earthquake, the Court was willing to apply s 9(1)(b).  Unlike December and April, this was the last of the earthquakes on which a claim was based and the second largest in order of magnitude.  As a result, it was not easily missed and there was an opportunity for the defendant to observe the state of the building afterwards (albeit some time later).

Expert witnesses

 Somewhat unusually, the Court was critical of the caucusing between experts in that it was not as successful as it ought to have been.  The Court stressed the need for actual and apparent independence of experts, early and meaningful discussions well in advance of trial, and constant professionalism (after one unfortunate incident).

Back to Summary Table

[1] Ridgecrest NZ Ltd v IAG New Zealand Ltd [2014] NZSC 129, click here for our review of the decision

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Privacy Commissioner to consult on Privacy Rules for Biometric Information
With the increasing use of facial recognition technology (FRT), retinal scans, and voice recognition by an array of different agencies, privacy concerns about its collection and use are set to be form...
24.11.2023 Posted in Business Advice
Fern forest NZ
Bioenergy in New Zealand: Fuels for the Future?
The energy transition from combustion fuels to low carbon alternatives is viewed as critical in the race to cut global CO2 emissions and reach climate targets.  We look at some of the opportunities p...
14.11.2023 Posted in Business Advice & Climate Change & Forestry
Will Wide BW
A well drafted will is a craft
The New Zealand do-it-yourself “DIY” attitude and way of life is not limited to home improvements, but sometimes also extends to wills.  Recently we had a DIY $5.99 fill in the blanks will acros...
07.11.2023 Posted in Private Wealth
rsz large pillars
Health and Safety: The Consequences of Dishonesty
Siddhartha Gautama said that lies are like huge, gaudy vessels, the rafters of which are rotten and worm-eaten, and that those who embark in them are fated to be shipwrecked.  Two remarkable health a...
03.11.2023 Posted in Employment & Health & Safety
Properly sequencing your Construction Adjudications: Henry Construction Projects Ltd v Alu-Fix (UK) Ltd
According to the UK’s Technology and Construction Court (TCC) (in Henry Construction Projects Ltd v Alu-Fix (UK) Ltd [2023] EWHC 2010) valid payment claims must be paid before the underlying merits ...
30.10.2023 Posted in Construction & Disputes
Key change to rules on distribution of surplus assets under the new Incorporated Societies Act 2022
On 5 October 2023, the new Incorporated Societies Act 2022 (2022 Act) came fully into force, replacing the Incorporated Societies Act 1908 (1908 Act). One of the key requirements under the 2022 Act is...
18.10.2023 Posted in Business Advice
Construction Framework Wide BW
Major milestone passed – NZS3910:2023 expected in time to fill Christmas stockings
As the most widely adopted standard form construction contract in NZ, NZS 3910 was more than ready for updated conditions given the changes in the industry since its last review in 2013.  After almos...
09.10.2023 Posted in Construction
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.