30.10.2023

Properly sequencing your Construction Adjudications: Henry Construction Projects Ltd v Alu-Fix (UK) Ltd

According to the UK’s Technology and Construction Court (TCC) (in Henry Construction Projects Ltd v Alu-Fix (UK) Ltd [2023] EWHC 2010) valid payment claims must be paid before the underlying merits are examined, even if this is done through construction adjudication.

New Zealand Courts do not appear to have addressed this issue.  However, because of similarities between the Construction Contracts Act 2002 (CCA) and the UK equivalent[1], it is possible that the same approach might be taken if tested in New Zealand.

Background[2]

Henry Construction Projects Ltd (Henry) as main contractor entered into a sub-contract with Alu-Fix (UK) Ltd (Alu-Fix).  Henry failed to issue the UK equivalent of a valid payment schedule and did not pay the amounts claimed by Alu-fix by the due date for payment under the contract.  Alu-Fix therefore commenced a payment claim adjudication.  While that adjudication was still ongoing, Henry issued a simultaneous “true value” adjudication.

A “true value” adjudication examines the underlying merits of a payment claim or payment schedule to determine what the “true value” of a payment claim actually is.  This should be contrasted against procedural “payment claim” adjudications, which only look at whether the relevant payment claim / payment schedule complies with the CCA[3], and therefore whether there is a debt due on the basis that a valid payment claim has been submitted.

Alu-Fix won the payment claim adjudication and Henry paid the amounts due in accordance with that determination.  Henry then won the “true value” adjudication, which decided that Henry had significantly overpaid Alu-Fix.  Alu-Fix did not pay the amount determined in the “true value” adjudication, which saw Henry issue court proceedings to enforce that decision.

Alu-Fix resisted enforcement on grounds that Henry had brought its “true value” adjudication prematurely, meaning that the adjudicator did not have jurisdiction.  This argument was based upon earlier UK case law[4] which indicated that parties had to pay outstanding amounts under a payment claim before they could commence a “true value” adjudication.  This had been expressed as simply an application of the “pay now, argue later” principle. 

High Court decision 

The High Court agreed with Alu-Fix: Henry had brought the “true value” adjudication prematurely, and so the adjudicator did not have jurisdiction.  It confirmed that an obligation to make payment in response to a payment claim arises on the date provided by the underlying contract or set out in the payment claim; not when an adjudicator subsequently decides that the payment claim is valid / there is no valid payment schedule in response.

The Court affirmed the earlier UK case law that there was a hierarchy to the provisions of the UK Act: the right to be paid had priority over the right to bring a “true value” adjudication.  Any other conclusion would compromise the “pay now, argue later” principle underlying the UK Act by allowing the parties to, in effect, “argue first” and then “pay later”.

Accordingly, Henry should have paid the amounts owing to Alu-Fix under the payment claim before commencing a “true value” adjudication.

The Court went on to note, however, that parties could start a “true value” adjudication before paying the amounts claimed in a payment claim in two specific situations:

  • Where a payment schedule had been provided with a zero value; and
  • Where the party bringing the “true value” adjudication was sufficiently confident that the payment claim was invalid (and, of course, where this eventually was proven to be the case in any payment claim adjudication on this issue). 

Comment 

To our knowledge, New Zealand does not appear to have either drawn a distinction between “true value” adjudications and other types of adjudications (eg payment claim adjudications) or addressed whether there is any hierarchy within the CCA.

However, the underlying rationale of the UK Act and New Zealand’s CCA (ie “pay now, argue later”) is the same, and the relevant statutory provisions of each piece of legislation are similar.[5]  With these similarities, it is possible that arguments similar to those deployed in Henry Construction Projects Ltd v Alu-Fix (UK) Ltd may be used by parties and accepted by decision makers here in New Zealand.

The best protection against these sorts of issues arising is to ensure that payment claims and payment schedules are issued on time and are substantively compliant.  All too often contracting parties fail to give sufficient attention to these details, leaving them unable to take advantage of or protect against the sudden death payment regime in the CCA.

If you have any questions about payment claims, payment schedules, the CCA or construction adjudications, please get in touch with our Construction Team or your usual contact at Hesketh Henry.

 

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

[1] The Housing Grants, Construction and Regeneration Act 1996 (UK Act).

[2] A note on terminology: for simplicity and ease of understanding for New Zealand readers, in this article we have used the CCA terms “payment claim” and “payment schedule” instead of the UK equivalent “payment application” and “pay less notice” when describing the UK proceedings.

[3] Or, in the UK, the UK Act.

[4] Including Grove Developments Ltd v S&T (UK) Ltd [2018] EWCA 2448 and Bexheat v Essex Services Group [2022] EWHC 936 (TCC).

[5] UK Act s 111:  ‘Where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment …

The payer or a specified person may in accordance with this section give to the payee a notice of the payer’s intention to pay less than the notified sum”; CCA s 20: “A payer becomes liable to pay the claimed amount on the due date for the payment to which the payment claim relates if—

(a) a payee serves a payment claim on a payer; and

(b) the payer does not provide a payment schedule to the payee…”.

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Rewriting the Risk: Lessons from John Sisk & Son Ltd v Capital & Centric (Rose) Ltd [2025] EWHC 594 (TCC)
A recent decision by the English High Court, John Sisk & Son Ltd v Capital & Centric (Rose) Ltd [2025] EWHC 594 (TCC), considered the interpretation of a risk allocation provision under a besp...
09.07.2025 Posted in Construction & Disputes
Can Contractors Terminate for Repeated Late Payment? Key Lessons from Providence v Hexagon
The decision of the English Court of Appeal in Providence Building Services Ltd v Hexagon Housing Association Ltd [2024] EWCA Civ 962 provides important guidance on a contractor’s termination right...
09.07.2025 Posted in Construction & Disputes
Property
Make Your Premises Good Again
With all the time, effort and cost that goes into taking on a new lease of commercial premises, what happens when it comes time to move on can seem unimportant. It is not surprising, then that make-go...
25.06.2025 Posted in Property
Flooded car
Flooding due to overland flow paths and damaged drainage
Persistent heavy rainfall across the country often results in damage to property due to flooding caused by overland flow paths and defective drainage.  But who is responsible for the cost of the dama...
17.06.2025 Posted in Climate Change & Property
Understanding Indirect Privacy Notification: What you need to know
The Privacy Amendment Bill (the Bill), if passed into law, will require agencies to notify individuals when their personal information is collected from a source other than the individual themselves, ...
16.06.2025 Posted in Corporate & Commercial & Employment
iStock  Succession Plan medium
Family Ties: Intra-Family Succession and Exit Planning
As the second instalment in a series of articles looking at the generational wealth transition and its impacts on business succession in New Zealand, Ben Hickson (partner, Corporate & Commercial...
16.06.2025 Posted in Corporate & Commercial & Private Wealth
Employment law at a glance – June 2025
If you are anything like us, you will be shocked to realise that we are halfway into 2025. As time has been marching on, so too have employment law developments – and there have certainly been quite...
05.06.2025 Posted in Employment
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.