09.07.2025

Rewriting the Risk: Lessons from John Sisk & Son Ltd v Capital & Centric (Rose) Ltd [2025] EWHC 594 (TCC)

A recent decision by the English High Court, John Sisk & Son Ltd v Capital & Centric (Rose) Ltd [2025] EWHC 594 (TCC), considered the interpretation of a risk allocation provision under a bespoke JCT Design and Build Contract.  The judgment also provided commentary on the interpretive weight of pre-contractual negotiations, and reaffirmed the courts’ consistent reluctance to give regard to negotiations that are not incorporated into the final contract.

Background

Capital & Centric (Rose) Ltd (C&C), as Principal, and John Sisk & Son Ltd (Sisk), as Contractor, entered into a bespoke JCT Design and Build Contract (Contract) for a major redevelopment project at Weir Mill, in Stockport, England.  The project involved complex works to both new and existing structures, including the integration of two historic mill buildings into the new development.

A key contractual issue emerged relating to who was responsible for the risks associated with the existing structures on site, particularly whether those buildings could support the proposed new works.  The Contract included a broad bespoke clause at 2.42, which provided that C&C gave no warranty or representation as to the condition of the site and existing structures, and that Sisk was deemed to have inspected and satisfied itself as to the site conditions and existing structures.

Clause 2.42 was stated to be subject to “item 2 of the Clarifications”, which was embedded within the Contract documents.  This line was at the centre of the dispute.  Item 2 of the Clarifications stated:

Sisk Clarification

Comments / Risk Owner

Existing Structures Risk including ability to support / facilitate proposed works

The Employer is to insure the Existing buildings/ works. Employer also to obtain warranty from Arup with regard to the suitability of the proposed works. Employer Risk

Sisk argued that Item 2 meant the Principal retained the risk for the suitability of the existing structures.  C&C disagreed, arguing that this item had no contractual effect or did not override the broader allocation of risk in clause 2.42.

The dispute first proceeded to adjudication, where the adjudicator found in favour of C&C on the basis that clause 2.42 placed the structural risk on Sisk and that Item 2 of the Contract Clarifications did not displace this.  Sisk disagreed with the adjudicator’s reasoning and sought a declaration in the High Court regarding the correct interpretation of the relevant Contract terms.

High Court Decision

The Court found in favour of Sisk, concluding that the contractual documents, properly interpreted, placed the risk associated with the suitability of existing structures on the Principal and not the Contractor.  This outcome turned on the effect of item 2 in the Contract Clarifications, which referred to “Employer Risk” in relation to the relevant structural matters.

The Judge held that bespoke provisions like the Contract Clarifications must be given full effect, even when they appear to modify or qualify standard form clauses such as 2.42.  It was concluded that the language used in the Clarifications was clear and that it effectively excluded the Contractor from liability for the structural suitability of the existing buildings.

The Court also considered the weight of the pre-contractual negotiations and their effect on the interpretation of the risk allocation provisions.  C&C sought to rely on its earlier purported refusal to accept responsibility for the existing structures.  C&C argued that this refusal reflected an agreement on risk allocation that should guide the interpretation of the final contract.  This argument was rejected by the Court, which maintained the status quo that such negotiations are generally inadmissible in construing the meaning of a written contract. 

Key Takeaways

This judgment confirms the significance of precise drafting and clear risk allocation.  It serves as an important reminder to have consistency between contractual documents, including the contract itself and any other technical or commercial documents that are appended to the contract.

A central lesson from this case is the limited interpretive weight given to pre-contractual negotiations and tender clarifications. The Court reiterated the principle that construction contracts must be interpreted objectively based on the final, agreed documents, and not on negotiation history or subjective intentions.

Relevance and Application in New Zealand

Although this case was decided under a UK JCT standard form contract, it has clear relevance for New Zealand construction law, especially in the context of NZS 3910.  Risk allocation under NZS 3910 is often amended by way of special conditions or schedules, and disputes can arise when those amendments conflict with general provisions of the standard form.

This decision highlights that if parties intend to shift risk, they must do so clearly and expressly.  It is not enough to rely on pre-contract exchanges or informal understandings. Courts in New Zealand, like their English counterparts, will focus on the final terms as recorded in the signed contract and will be slow to rely on negotiation history unless very specific legal doctrines apply.

If you have any questions about construction contracts, please get in touch with our Construction Team or your usual contact at Hesketh Henry.

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Library BW
Director Residential Address Protection – Bill is passed into law
Last week, the Companies (Address Information) Amendment Act 2025 (the Act) was enacted.  The Act permits directors who have serious concerns about the disclosure of their residential address to elec...
24.11.2025 Posted in Corporate & Commercial
Business Succession Planning – Shareholder Agreements What have you and your co-investors agreed?
A successful exit from a business can be, and often is, affected by the steps you take when setting up the business. Although there are various business structures that can be used in New Zealand, by ...
06.11.2025 Posted in Corporate & Commercial & Private Wealth
Post-Employment Obligations – Worth the Paper They Are Written On?
“Gone are the days … when an employee could confidently sign up to a restraint and then breach it in the bold expectation that ‘those things are not worth the paper they are written on’”.[1]...
22.10.2025 Posted in Employment
Proportionate Liability – the Next Evolution?
The current line of authorities establishing the ability for building owners to be able to claim in negligence for the cost of rectifying defects can be traced to the Court of Appeal’s (COA) judgmen...
17.10.2025 Posted in Construction & Insurance
New Zealand’s Resource Management Reform: Understanding the 2025 Amendment Act’s Transformative Changes to Fines and Insurance Coverage
Introduction The resource management landscape in New Zealand has undergone a seismic shift with the recent passage of the Resource Management (Consenting and Other System Changes) Amendment Act 2025,...
10.09.2025 Posted in Regulatory
vecteezy a man in a suit is holding his finger to his lips   Extended fade cropped
Pay secrecy no more – what you need to know about the most recent employment law change
Conversations about what employees earn are no longer prohibited or required to be shrouded in secrecy. The Employment Relations (Employee Remuneration Disclosure) Amendment Bill came into force on 27...
29.08.2025 Posted in Employment
HH Pg  Wave alternative
The America’s Cup Partnership and the Deed Of Gift: Navigating Legal Tensions
The newly released protocol (Protocol) for the 38th America’s Cup (AC38) marks another chapter in the evolution of the world’s oldest international sporting trophy.  While the Protocol introduces...
26.08.2025 Posted in Disputes & Private Wealth & Trade and Transport
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.