17.09.2024

UK Supreme Court: Are collateral warranties considered construction contracts?

The UK Supreme Court recently released Abbey Healthcare (Mill Hill) Ltd v Augusta 2008 LLP (formerly Simply Construct (UK) LLP) [2024] UKSC 23 determining that a collateral warranty used in the construction context was not a construction contract under the Housing Grants, Construction and Regeneration Act 1996 (the Act) for the purposes of a right to adjudication.  A collateral warranty is an agreement with a third party to provide that party rights in respect of defective works. 

Augusta 2008 LLP (Formerly Simply Construct (UK) LLP) (Simply) was engaged as a contractor by Sapphire Building Services Ltd (Sapphire), with the contract later novated to Toppan Holdings (Toppan) for the construction of a care home in Mill Hill, London (Property).  The tenant of the Property was Abbey Healthcare (Mill Hill) Ltd (Abbey).  

In 2018, alleged construction defects were discovered which Simply refused to remediate, resulting in Abbey bearing the costs of the remedial work.  Fast forward to 2020, Toppan requested a collateral warranty to be provided to Abbey.  Following proceedings for specific performance, Simply entered into the collateral warranty with Abbey (Abbey Collateral Warranty).  The dispute arose in late 2020 following adjudication proceedings commenced by Toppan and Abbey against Simply for the defective work and cost of remedial works. 

Judicial History

From commencement, the case has experienced significant judicial analysis as to whether a collateral warranty is a construction contract.  Initially, the Adjudicator rejected Simply’s challenge that the Abbey Collateral Warranty was not a construction contract for the purposes of section 104(1) of the Act.  The Technology and Construction Courts (TCC) judge took an opposing view.  The summary judgment application by Abbey was dismissed on the grounds that the Abbey Collateral Warranty was not a construction contract.  On appeal to the Court of Appeal, the majority adopted a contrary view that a collateral warranty may be a construction contract, and timing of the entering of the warranty was not relevant.  The Abbey Collateral Warranty was considered retrospective and prospective.  Notably, Coulson LJ found that “it is a warranty as to future performance” therefore could still amount to a construction contract.

Supreme Court Judgment 

On appeal, the Supreme Court had two issues to determine:

  • A statutory interpretation question on section 104(1) of the Act to ascertain the meaning of an agreement “for… the carrying out of construction operations”; and
  • A contractual interpretation exercise of how to construe the Abbey Collateral Warranty and, so construed, whether it fell within the scope of s 104(1).

On the first issue, the Court made an important distinction that s 104 requires an agreement for which the purpose or object of the agreement is the carrying out of construction operations.  The distinction arises as the warranty which merely promises the work will be performed does not give rise to a “distinct or separate obligation” to carry out the work beyond the original construction contract.  The nature of a derivative promise and lack of direct contractual obligation precludes the ability of a collateral warranty to be enforced as a construction contract.

On the second issue, the Court considered the majority’s interpretation of the collateral warranty did in part provide for future performance and it does amount to a promise to carry out the works.  Yet the Court noted the majority’s undue weight on the wording which merely amounts to a derivative promise. The contractor is not promising anything beyond their obligations to the employer.  Rather, the collateral warranty needs to be expressed in such terms to cover both past and future obligations.  Where the contractor is warranting performance of existing obligations under the contract, the warranty will not be an agreement for the carrying out of construction.

The Court’s judgment favoured the approach that the dividing line for collateral warranties be those that replicate the undertakings provided in the head contract and those that give rise to a separate and distinct obligation to carry out construction. On this approach, most collateral warranties will not be construction contracts for the purposes of the Act.  This reinforces the certainty that collateral warranties generally fall outside of the Act.

New Zealand’s Approach

The Supreme Court’s approach to collateral warranties provides some guidance on their potential treatment in New Zealand.  The Construction Contacts Act 2002 creates a statutory right to adjudication for parties to a construction contract.  A construction contract is defined as a “contract for carrying out construction work” (s 5).  

NZS3910:2023 schedule 13 provides for the inclusion of a standard form warranty.  While the express words of the warranty will always prevail, unamended, this standard form warranty is unlikely to be a construction contract.

If you have any questions about this article, please get in touch with our Construction Team or your usual contact at Hesketh Henry.

 

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

 

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Rewriting the Risk: Lessons from John Sisk & Son Ltd v Capital & Centric (Rose) Ltd [2025] EWHC 594 (TCC)
A recent decision by the English High Court, John Sisk & Son Ltd v Capital & Centric (Rose) Ltd [2025] EWHC 594 (TCC), considered the interpretation of a risk allocation provision under a besp...
09.07.2025 Posted in Construction & Disputes
Can Contractors Terminate for Repeated Late Payment? Key Lessons from Providence v Hexagon
The decision of the English Court of Appeal in Providence Building Services Ltd v Hexagon Housing Association Ltd [2024] EWCA Civ 962 provides important guidance on a contractor’s termination right...
09.07.2025 Posted in Construction & Disputes
Property
Make Your Premises Good Again
With all the time, effort and cost that goes into taking on a new lease of commercial premises, what happens when it comes time to move on can seem unimportant. It is not surprising, then that make-go...
25.06.2025 Posted in Property
Flooded car
Flooding due to overland flow paths and damaged drainage
Persistent heavy rainfall across the country often results in damage to property due to flooding caused by overland flow paths and defective drainage.  But who is responsible for the cost of the dama...
17.06.2025 Posted in Climate Change & Property
Understanding Indirect Privacy Notification: What you need to know
The Privacy Amendment Bill (the Bill), if passed into law, will require agencies to notify individuals when their personal information is collected from a source other than the individual themselves, ...
16.06.2025 Posted in Corporate & Commercial & Employment
iStock  Succession Plan medium
Family Ties: Intra-Family Succession and Exit Planning
As the second instalment in a series of articles looking at the generational wealth transition and its impacts on business succession in New Zealand, Ben Hickson (partner, Corporate & Commercial...
16.06.2025 Posted in Corporate & Commercial & Private Wealth
Employment law at a glance – June 2025
If you are anything like us, you will be shocked to realise that we are halfway into 2025. As time has been marching on, so too have employment law developments – and there have certainly been quite...
05.06.2025 Posted in Employment
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.