03.07.2015

Body Corporate 326421 v Auckland Council [2015] NZHC 862

This was a substantial claim for construction and design defects in a 12 floor apartment building called the Nautilus.  The unit owners and Body Corporate sued the Council, the head contractor, the architect, the cladding subcontractor and the tiler.  They were largely successful, and were awarded $25.07 million in total.  However, most of the defendants were insolvent: only the Council and the tiler (whose liability was limited to certain defects) remained.

The head contractor was Brookfield Multiplex Constructions (NZ) Ltd (in liquidation) (BMX).  It was found liable for all of the defects.  A question arose as to whether a professional indemnity policy held by BMX, under which Zurich Insurance plc was the lead underwriter, would respond to the claim.

Under the policy, BMX was covered for contractual or other claims arising out of negligent performance of “Professional Activities and Duties”.  That cover extended to any negligent acts of consultants prior to novation of the consultancy agreement to BMX.   “Professional Activities and Duties” meant activities undertaken by, or under the supervision of professionally qualified persons of at least five years relevant experience, but excluded day-to-day supervision of construction work.  The policy also excluded claims arising out of defective workmanship or materials, unless the claim related to the negligent design of materials or the negligent specification or selection of materials.

Although the consultancy agreement between the developer and the architect had been novated to BMX, the terms of the novation excluded liability for the design of the Nautilus, other than for minor errors and omissions which an experienced contractor would be expected to foresee, or design changes introduced for BMX’s benefit.

BMX had the onus of establishing that every defect for which indemnity was sought came within the insuring clause, including the “Professional Activities and Duties” definition.  The underwriters had the onus of proving that the exclusion then applied to exclude BMX’s claim in relation to each defect.

The Court held that if a claim had multiple causes, it would be covered if one of the causes fell within the insuring clause, provided none of the causes fell within the exclusion for defective workmanship or materials.  A “cause” need not be the proximate cause, it could be simply a material contributing factor.  If defective workmanship was a material contributing factor to any particular defect, the claim in relation to that defect would be excluded.

The Court examined each cause of action set out in the statement of claim.  The plaintiffs’ claim against BMX for breach of the head contract (which was assigned to the plaintiffs by the developer) was for failure to correct defective workmanship and materials in the defects liability period.  There was no allegation of defective design, and the insuring clause was not activated.

The plaintiffs’ claim in negligence was for a breach of a duty of care “relating to design and construction issues”.  Those issues included modifying the design of the cladding system, construction of the Nautilus with the defects and failing to rectify the defects during the defects liability period.  The underwriters claimed that defective workmanship was a material contributing cause in respect of all such losses.  A review of each of the defects and their proven causes indicated that poor or defective workmanship was indeed a material cause of each head of loss.  As a result, the policy did not respond to any part of the plaintiffs’ claim.

This case demonstrates the limitations of professional indemnity policies for head contractors, and a potential exposure for principals if the contractual design risk is shifted from the design consultant to the head contractor.  While BMX only assumed a limited design risk under the terms of its novation, had the complete risk in fact been transferred, the exclusion in the policy would have applied to all claims for defective design.

Back to Summary Table

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

UK Court of Appeal rules that that courts can order parties to engage in ADR: Churchill v Merthyr Tydfil County Borough Council [2023] EWCA Civ 1416
The England and Wales Court of Appeal (EWCA) has held that in certain circumstances, the courts can order parties to engage in alternative dispute resolution (ADR) or stay proceedings to allow the par...
24.07.2024 Posted in Construction & Disputes
Health and Safety Tiles
Updated Guidance: IOD and WorkSafe release ‘Health and Safety Governance – A Good Practice Guide’
While we wait with bated breath for the outcome in the prosecution of former Ports of Auckland CEO, Tony Gibson, officers’ duties are very much at the forefront of everyone’s mind. Section 44 of t...
23.07.2024 Posted in Employment & Health & Safety
Knowing your limits: High Court confirms liability caps in engineering consultancy agreements are consistent with Building Act duties
Design errors in a construction project can result in millions of dollars in loss.  Standard form consultancy agreements typically limit the amount that can be recovered for such errors.  The cap on...
09.07.2024 Posted in Construction & Disputes
glenn carstens peters npxXWgQZQ unsplash
Sender beware – how private are digital workplace conversations?
Following on from the recent Official Information Act request for correspondence between Ministry of Justice employees, employees may be wondering how private their online conversations with colleague...
04.07.2024 Posted in Employment
Concrete pillars impressive
TCC confirms Slip Rule limits in Adjudications
The Technology and Construction Court (TCC) has confirmed the narrow parameters of the ‘slip rule’ in the UK, which allows adjudicators to amend their determination to correct for any clerical or ...
02.07.2024 Posted in Construction & Disputes
Scots rule standard notification clause was condition precedent
In a warning for contractors, a Scottish Court has ruled that a standard form notification clause was a condition precedent to recovering time-related costs (TRCs) (FES Ltd v HFD Construction Group Lt...
01.07.2024 Posted in Construction
rape blossom
Anticipatory Repudiatory Breach and the Date of Default: Ayhan Sezer v Agroinvest
The decision in Ayhan Sezer v Agroinvest [2024] EWHC 479 (Comm) clarifies that where there has been an anticipatory repudiatory breach of contract, the “date of default” is the date of the breach ...
25.06.2024 Posted in Trade and Transport
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.