18.06.2018

Custom Street Hotel Ltd v Plus Construction NZ Ltd [2017] NZCA 36

This was an unsuccessful appeal by Custom Street Hotel Ltd (Custom) from a High Court decision (originally appealed from an arbitral award) which considered the meaning of the termination provisions in NZS 3910:2003 (the predecessor to NZS 3910:2013).

Background

The parties entered into a $14.45m contract to convert an existing building into a hotel.  The project was inundated with issues.  The contractor, Plus Construction NZ Ltd (Plus), blamed Custom’s failure to obtain consents, while Custom asserted that Plus could still progress the works and had under-resourced the project and ultimately walked off the job.

Plus issued a default notice under clause 14.3.1(b) for two unpaid payment claims totalling c$258,000.   Under the contract, Custom had 10 working days to pay otherwise suspension/termination rights would arise.  During the 10 working days, the Engineer suspended the works at Custom’s behest alleging Plus was in breach of site safety requirements.  Custom did not pay the outstanding amount within the required time and Plus then purported to require the Engineer to suspend the contract works under clause 14.3.3 (although this was already suspended).  The next day Plus wrote giving notice of termination and Custom also paid the claimed amount.

Custom challenged the validity of Plus’ termination and issued its own notice of default, which included a contention that Plus had abandoned the contract.  Plus, operating on the basis that it had already validly terminated, did not act on Custom’s notice.  Custom therefore, purported to terminate the contract itself on the basis that Plus’s termination was invalid, and claimed damages from Plus for the increased cost of the having the works completed by another contractor.  Custom also sought to call up a performance bond which required certification by the Engineer.

The parties referred these issues to arbitration. In the meantime, they agreed the bond monies would be placed in escrow pending the outcome.  By this time the Engineer had also certified that $24.9m was due to Custom for the additional costs of another contractor completing the works.

The arbitrator found Plus had validly terminated the contract and could not have been in default when the Engineer issued his default certificate.  The arbitrator also found the Engineer had wrongly certified payment of $24.9m, and that a claim for additional costs to complete the work was governed by clause 14.2.4 and could only be determined on completion of the works.

Unsuccessful on appeal in the High Court, Custom further appealed to the Court of Appeal (CA) on specific points of law.

Repudiation disentitling termination

Custom argued that Plus was not entitled to terminate because it had repudiated the contract by ceasing work, removing scaffolding and breaching health and safety requirements.  However, the arbitrator held that there was nothing to indicate Plus was not committed to the contract.

The CA, agreeing with the arbitrator and High Court, that a breach by Plus did not need to be repudiatory before they would be disentitled from terminating the contract.  Something less, such as breaching an essential term or a serious breach under s 7 of the Contractual Remedies Act 1979 (CRA) (now, the Contract and Commercial Law Act 2017 (CCLA)), may suffice.  However, for such a breach to disentitle the party from terminating, it would have to mean that it would otherwise benefit from its own wrong.  Here, Plus had not repudiated or breached an essential term, meaning the question of whether it was disentitled from terminating did not arise.

Termination by contractor under clause 14.3.3

Under clause 14.3.3, if the principal is in default the contractor can give 10 working days notice to remedy the default.  If the default is not remedied, the contractor can require the Engineer to suspend the work and, following that suspension, the contractor can terminate.  In this case, the Engineer had not acted on Plus’ request to suspend as the works were already suspended at the behest of Custom. Custom contended that both the notice to suspend and the suspension were required before termination under clause 14.3.3 could occur based on the words “following such suspension”. Adopting a purposive interpretation, the CA rejected this – holding that actual suspension was not required under clause 14.3.3 before the contractor could terminate.  It was enough that a right to suspend arose before termination.

Additional costs to complete under clause 14.2.4

Custom claimed from Plus the projected additional costs of having another contractor complete the works under clause 14.2.4.  The CA agreed with the High Court that the quantum of any such claim under clause 14.2.4 could only be assessed once the works were completed, and could not be based on projected costs. Its reasoning was five-fold.  Clause 14.2.4 says specifically “on completion of the Contract Works”.  Second, an interpretation that required splitting the works within clause 14.2.4 would be an awkward and unnatural interpretation that would not have been intended in this type of contract.  Third, clause 14.2.4 follows in sequence with clause 14.2.3 (principal resuming possession).  Fourth, the language of clause 14.2.4 presumes the works are completed.  Finally, given the certification process under clause 14.2.4 may lead to a payment being made to the contractor, this indicated the wash-up task in 14.2.4 would only occur after completion since any further payments to the contractor are suspended until then.

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

shutterstock
Bowen case part 2 – the ins and outs of the determination
In our last article, we wrote about what protected disclosures are and who can make them. In this article, we discuss the Employment Relations Authority (Authority) determination, Bowen v Bank of New ...
13.09.2024 Posted in Employment
Are trustees bound to relationship property agreements?
In Rawson v Prescott [2024] NZHC 1919, the High Court addressed a dispute involving trust property and a relationship property agreement. Mr RR, trustee of the GR Family Trust, sought summary judgment...
10.09.2024 Posted in Private Wealth
shutterstock
Bowen case part 1 – blowing the whistle
You may have heard of the term ‘whistleblowing’, but have you heard of ‘protected disclosures’? Protected disclosures are a creature of the Protected Disclosures (Protection of Whistleblowers)...
10.09.2024 Posted in Employment
Construction theme black and white
Contractors take note – are any of your retentions clauses prohibited provisions?
In Stevensons Structural Engineers 1978 Ltd (in liq) v McMillan & Lockwood (PN) Ltd & Anor [2024] NZHC 2415, the High Court held that the timing for payment out of retentions in certain subcon...
05.09.2024 Posted in Construction
Avoiding the Grey Area: Interpreting Trust Beneficiary Classes
Beneficiary classes in trust deeds should be clearly defined to ensure the assets of the trust benefit the people who the settlor(s) of the trust originally intended.   If they are not, then disputes...
05.09.2024 Posted in Private Wealth
vecteezy square wooden blocks lined up on a wooden workbench  Insurance Icons centered
Hesketh Henry’s Insurance Team author LexisNexis Practical Guidance Insurance
Hesketh Henry’s Insurance Team is delighted to celebrate the launch of Practical Guidance Insurance. LexisNexis has launched Practical Guidance Insurance containing 12 topics and over 50 sub-topics ...
03.09.2024 Posted in Insurance
Contract dictionary
Is ‘close enough’ OK? Reasonable endeavours to overcome a force majeure event
The English Supreme Court’s decision in RTI Ltd v MUR Shipping BV [2024] UKSC 18 has demonstrated the effect sanctions may have on a contract as a force majeure event and clarified the parameters of...
03.09.2024 Posted in Trade and Transport
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.