17.12.2015

Parkin v Vero Insurance New Zealand Ltd [2015] NZHC 1675

This decision will be welcomed by insurers.  It provides judicial confirmation that “jacking and packing” can be an acceptable method of re-levelling and repairing floors that have suffered differential settlement.

Background

Mr Parkin’s townhouse, which had been constructed in early 2009, was damaged by the September 2010 and February 2011 earthquakes.  The property was initially in the “white zone”, but this was eventually replaced with a green zone classification.

Mr Parkin’s insurer, Vero, concluded it was economic to repair his house, and proposed doing so by jacking and packing the piles to remedy floor dislevelment.

Mr Parkin was unhappy with Vero’s proposal and considered the house should be re-built.  He contended that Vero was obliged to return the house to essentially an identical condition to what it was prior to the earthquakes, bearing in mind the house was less than two years old at the time of the first earthquake.  He also sought payment of the estimated reinstatement costs before these costs were actually incurred, and alleged that Vero was in breach of implied terms of good faith and the Fair Insurance Code (Code) in relation to its claims handling process.  These claims were rejected by the High Court.

Standard of repair

This was a “when new” type policy.  Vero had the option to pay either (1) the cost incurred in “repairing the damaged portion … to a standard or specification no more extensive, nor better than its condition when new” or (2) the indemnity value if the house was not repaired or rebuilt by Mr Parkin within 12 months, unless Vero agreed to extend this period.

Mander J observed that “when new” suggests a narrower or stricter basis for comparison than “as new”, which conveys a broader sense of comparison.  Notwithstanding this, His Honour rejected Mr Parkin’s “identical replica” argument (ie that all damage must be replaced like-for-like).   If that argument was correct, it would render superfluous the concept of repair, which the policy expressly included and clearly contemplated.

Mander J drew a distinction between structural or functional components and those which have aesthetic purpose.  Where an item has only a functional purpose, so long as the remedial strategy restores that functional purpose to a “when new” condition, the policy obligation will be met.  That condition may be achieved by repair rather than replacement.

In this case, the fact that the house was reasonably new and did not previously have packers between the piles and bearers was of no consequence.  The purpose of a pile and the foundation system as a whole is substantially, if not entirely, structural.  Packers would not affect the structural integrity of the floor and they would not be visible except during a sub-floor inspection, meaning there was little or no aesthetic value attached to their use.

Payment obligation

Following the Court of Appeal in Medical Assurance Society v East [2015] NZCA 250, Mander J confirmed that Mr Parkin must actually incur the costs of remediating his property before Vero’s obligation to pay the reinstatement sum is triggered.  Absent Vero opting to pay the indemnity value, Mr Parkin had no entitlement to an advance cash payment based on the estimated cost of repair.

Breach of good faith/Fair Insurance Code

Mr Parkin also made what might be considered novel arguments regarding good faith and the Code.  He claimed Vero was in breach of these alleged implied obligations by failing to explain his policy entitlements or how the policy was intended to operate, and that Vero did not manage the claim in accordance with his policy entitlements, but applied its own internal management procedure, which did not follow the policy terms.  Much of this was based around an alleged misapprehension by Mr Parkin that Vero would undertake the reinstatement.

Mander J did not directly address the question of whether these terms were implied into the insurance contract.  Instead, His Honour was not satisfied there had been a breach of any such term, whether implied or otherwise.  In particular, Vero had introduced a claims management process to handle the large wave of earthquake claims, and there was no evidence that Vero had acted unfairly or had been unresponsive.  It appears that Mr Parkin’s real frustration lay with Vero’s assessment that his house could be repaired and the resulting impact on the claims settlement process when he disagreed with that assessment.  However, as note above, Vero’s repair strategy was upheld by the Court.

Back to Summary Table

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Privacy Commissioner to consult on Privacy Rules for Biometric Information
With the increasing use of facial recognition technology (FRT), retinal scans, and voice recognition by an array of different agencies, privacy concerns about its collection and use are set to be form...
24.11.2023 Posted in Business Advice
Fern forest NZ
Bioenergy in New Zealand: Fuels for the Future?
The energy transition from combustion fuels to low carbon alternatives is viewed as critical in the race to cut global CO2 emissions and reach climate targets.  We look at some of the opportunities p...
14.11.2023 Posted in Business Advice & Climate Change & Forestry
Will Wide BW
A well drafted will is a craft
The New Zealand do-it-yourself “DIY” attitude and way of life is not limited to home improvements, but sometimes also extends to wills.  Recently we had a DIY $5.99 fill in the blanks will acros...
07.11.2023 Posted in Private Wealth
rsz large pillars
Health and Safety: The Consequences of Dishonesty
Siddhartha Gautama said that lies are like huge, gaudy vessels, the rafters of which are rotten and worm-eaten, and that those who embark in them are fated to be shipwrecked.  Two remarkable health a...
03.11.2023 Posted in Employment & Health & Safety
Properly sequencing your Construction Adjudications: Henry Construction Projects Ltd v Alu-Fix (UK) Ltd
According to the UK’s Technology and Construction Court (TCC) (in Henry Construction Projects Ltd v Alu-Fix (UK) Ltd [2023] EWHC 2010) valid payment claims must be paid before the underlying merits ...
30.10.2023 Posted in Construction & Disputes
Key change to rules on distribution of surplus assets under the new Incorporated Societies Act 2022
On 5 October 2023, the new Incorporated Societies Act 2022 (2022 Act) came fully into force, replacing the Incorporated Societies Act 1908 (1908 Act). One of the key requirements under the 2022 Act is...
18.10.2023 Posted in Business Advice
Construction Framework Wide BW
Major milestone passed – NZS3910:2023 expected in time to fill Christmas stockings
As the most widely adopted standard form construction contract in NZ, NZS 3910 was more than ready for updated conditions given the changes in the industry since its last review in 2013.  After almos...
09.10.2023 Posted in Construction
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.