28.07.2021

Subcontractor entitled to raise set-off claim against principal’s warranty claim

A recent High Court case examined the all too common situation where a contractor goes into liquidation, but there are unresolved matters on a construction project affecting both the principal and subcontractor.  In Asphalt Supply Company Ltd v Cole John Ltd [2021] NZHC 1257 particular circumstances meant the principal was able to directly pursue the subcontractor for defective works, while the subcontractor equally could set-off amounts unpaid to it by the contractor.

Background

Cole John Ltd (CJL) engaged Complete Ltd (Complete) to undertake construction work.  In turn, Complete engaged Asphalt Supply Company Ltd (ASCO) as a subcontractor to complete certain asphalt work. 

Once ASCO had carried out its subcontracted work, Complete refused to pay the balance of the contract price (c $80K), on the basis it was payable upon ‘completion’, and because it alleged the work was defective it was not complete.  Complete promised to pay the balance upon receipt from ASCO of a six month warranty in favour of CJL.  Despite ASCO providing the warranty, Complete did not pay and promptly went into liquidation.

There was no direct contractual arrangement between ASCO and CJL, so ASCO was unable to recover the balance from CJL directly.  When CJL claimed against ASCO for a breach of the warranty and negligence in respect of the defective work, ASCO argued it was entitled to set off, against any damages in CJL’s favour, the balance left unpaid by Complete.  ASCO was unsuccessful in the District Court, and c $130K damages were awarded against it.

ASCO succeeds on appeal

On appeal, the High Court agreed that CJL was entitled to rely on the warranty, the work was indeed defective, and CJL’s loss was correctly quantified.  However, it allowed the appeal, finding the work was complete (albeit defective) and ASCO was therefore entitled to set-off the unpaid balance against CJL’s warranty claim.

The ability for ASCO to set-off the unpaid balance against the warranty claim was a result of s 18(2) of the Contract and Commercial Law Act 2017 (CCLA).  That section provides that a party in ASCO’s position has available, by way of a defence, set-off, or otherwise, any matter that would have been available to it:

  • if CJL had been a party to the contract in which the warranty was contained; or
  • if CJL was the promisee (ie Complete), the warranty had been made for the benefit of the promisee, and the proceeding had been brought against ASCO by the promisee.

Had Complete sued ASCO for the defective work, the measure of damages would have had to make an allowance for the balance of the contract price.  The normal measure of damages for incomplete or defective work under a construction contract is the cost of completing the work or remedying the defects, less any sum that would have been payable to the contractor had the work been properly carried out. Otherwise, the plaintiff would be overcompensated.

Under s 18(2) of the CCLA, the same allowance had to be made when CJL sued as the beneficiary of the warranty.  As a result, the unpaid balance was offset against CJL’s damages, which were reduced to c $50K.

Our comment 

The facts of this case will be familiar to many construction projects.  As with any project, there are a number of parties, not all of whom will have direct contractual relationships with each other.  Contractual arrangements must be carefully considered, particularly where solvency concerns arise.  Equally, the terms of any warranties and the specific wording of warranties should be carefully considered, including for whose benefit the warranty is provided.  Careful consideration, with legal input as appropriate, is required.

If you wish to discuss this case or any matters arising out of this decision or construction projects generally please contact our Construction Team or your usual contact at Hesketh Henry.

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

 

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Deciding to Wind Up? Observations on winding-up a trust from a recent High Court case
A trust can be a hassle and expensive to maintain.  So, it is not unusual for clients to reflect on whether a trust should be maintained. When settlors, Bert and Diana Queenin, decided to wind up the...
24.03.2025 Posted in Private Wealth
Mediation wide BW
Employment Law’s Dispute Resolution Process – Mediation
Navigating the dispute resolution process in the employment jurisdiction can be tricky. This article aims to spell out the key considerations for those involved in or contemplating mediation, which is...
24.03.2025 Posted in Employment
empty wallet finance concept
Amendment to the Crimes Act 1961: Intentionally not paying employees their wages now deemed theft
An amendment to the Crimes Act 1961 (Crimes Act) – the Crimes (Theft by Employer) Amendment Bill has been passed by Parliament and received Royal assent. It is now an enforceable provision of th...
14.03.2025 Posted in Employment
Time’s Up: Late Redelivery and the Assessment of Damages in Hapag Lloyd AG v Skyros Maritime Corporation and Hapag Lloyd AG v Agios Minas Shipping Company
The English Commercial Court gave an instructive judgment on the assessment of damages in Hapag Lloyd AG v Skyros Maritime Corporation and Hapag Lloyd AG v Agios Minas Shipping Company; an appeal brou...
11.03.2025 Posted in Trade and Transport
Team Hands in small
Cartel conduct: Do not pass “GO”, go directly to jail
Until 8 April 2021, cartel conduct was punishable only by civil penalty in New Zealand.  In R v Kumar [2024] NZHC 3955 the High Court imposed the first criminal convictions and sentences for cartel c...
06.03.2025 Posted in Construction & Disputes
Employment
2025 Insights: Proposed Legislative Changes and Employment Team Update
Team update and proposed legislative change – hello from the Hesketh Henry Employment Law Team 2025. Click here
20.02.2025
photo  dbe
When Sweet Turns Sour: The Costly Consequences of Contamination
The New Zealand Sugar Company (NZSC), trading as Chelsea Sugar, recently found itself in hot water after being fined nearly $149,500 by the District Court due to a prosecution brought by the Ministry ...
19.02.2025 Posted in Insurance & Trade and Transport
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.