28.07.2021

Subcontractor entitled to raise set-off claim against principal’s warranty claim

A recent High Court case examined the all too common situation where a contractor goes into liquidation, but there are unresolved matters on a construction project affecting both the principal and subcontractor.  In Asphalt Supply Company Ltd v Cole John Ltd [2021] NZHC 1257 particular circumstances meant the principal was able to directly pursue the subcontractor for defective works, while the subcontractor equally could set-off amounts unpaid to it by the contractor.

Background

Cole John Ltd (CJL) engaged Complete Ltd (Complete) to undertake construction work.  In turn, Complete engaged Asphalt Supply Company Ltd (ASCO) as a subcontractor to complete certain asphalt work. 

Once ASCO had carried out its subcontracted work, Complete refused to pay the balance of the contract price (c $80K), on the basis it was payable upon ‘completion’, and because it alleged the work was defective it was not complete.  Complete promised to pay the balance upon receipt from ASCO of a six month warranty in favour of CJL.  Despite ASCO providing the warranty, Complete did not pay and promptly went into liquidation.

There was no direct contractual arrangement between ASCO and CJL, so ASCO was unable to recover the balance from CJL directly.  When CJL claimed against ASCO for a breach of the warranty and negligence in respect of the defective work, ASCO argued it was entitled to set off, against any damages in CJL’s favour, the balance left unpaid by Complete.  ASCO was unsuccessful in the District Court, and c $130K damages were awarded against it.

ASCO succeeds on appeal

On appeal, the High Court agreed that CJL was entitled to rely on the warranty, the work was indeed defective, and CJL’s loss was correctly quantified.  However, it allowed the appeal, finding the work was complete (albeit defective) and ASCO was therefore entitled to set-off the unpaid balance against CJL’s warranty claim.

The ability for ASCO to set-off the unpaid balance against the warranty claim was a result of s 18(2) of the Contract and Commercial Law Act 2017 (CCLA).  That section provides that a party in ASCO’s position has available, by way of a defence, set-off, or otherwise, any matter that would have been available to it:

  • if CJL had been a party to the contract in which the warranty was contained; or
  • if CJL was the promisee (ie Complete), the warranty had been made for the benefit of the promisee, and the proceeding had been brought against ASCO by the promisee.

Had Complete sued ASCO for the defective work, the measure of damages would have had to make an allowance for the balance of the contract price.  The normal measure of damages for incomplete or defective work under a construction contract is the cost of completing the work or remedying the defects, less any sum that would have been payable to the contractor had the work been properly carried out. Otherwise, the plaintiff would be overcompensated.

Under s 18(2) of the CCLA, the same allowance had to be made when CJL sued as the beneficiary of the warranty.  As a result, the unpaid balance was offset against CJL’s damages, which were reduced to c $50K.

Our comment 

The facts of this case will be familiar to many construction projects.  As with any project, there are a number of parties, not all of whom will have direct contractual relationships with each other.  Contractual arrangements must be carefully considered, particularly where solvency concerns arise.  Equally, the terms of any warranties and the specific wording of warranties should be carefully considered, including for whose benefit the warranty is provided.  Careful consideration, with legal input as appropriate, is required.

If you wish to discuss this case or any matters arising out of this decision or construction projects generally please contact our Construction Team or your usual contact at Hesketh Henry.

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

 

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

vecteezy calendar and santa on table happy new year and xmas concept  ext e
Let me check my calen-deer – Leave entitlements over the festive period
What you need to know about holiday and leave entitlements over the festive season
18.12.2024 Posted in Employment
Health and Safety obligations for officers – Maritime NZ v Tony Gibson
At 146 pages, and 504 paragraphs, the recent Maritime NZ v Tony Gibson judgment is certainly not short on detail.[1] This is unsurprising given the complex factual matrix and landmark nature of this c...
17.12.2024 Posted in Employment & Health & Safety
nicholas doherty pONBhDyOFoM unsplash e
Energy Spotlight: Offshore Renewable Energy Bill introduced to Parliament
Last week the Offshore Renewable Energy Bill (Bill) was introduced into Parliament.  The Bill is the culmination of the discussion and consultation processes commenced by the Ministry of Business Inn...
17.12.2024 Posted in Climate Change & Corporate & Commercial
Court of Appeal clarifies purchasers’ and contractors’ creditor liquidation status when suppliers of prefabricated products go insolvent
Prior to the Court of Appeal’s decision in Francis v Gross [2024] NZCA 528 on 17 October 2024 (Podular (COA)), there was a period of uncertainty for building contractors as to their status in respec...
r gray KJdRtmTIIs unsplash BW med
New Conditions for the UK Standard Conditions for Towage and Other Services
In November 2024 a new edition of the UK Standard Conditions for Towage and Other Services (the UKSCT 2024) was issued by the British Tugowners Association. The UK Standard Conditions for Towage are c...
12.12.2024 Posted in Trade and Transport
James Hardie New Zealand Ltd v Zurich Australian Insurance Ltd: Rebuffing a stay of proceedings
In James Hardie New Zealand Ltd v Zurich Australian Insurance Ltd [2024] NZHC 3126, the High Court refused to grant a stay of proceedings under ss 22 and 25 of the Trans-Tasman Proceedings Act 2010 (A...
12.12.2024 Posted in Construction & Insurance
aviation
Sky’s the Limit: ICAO Announces Increase of Airlines’ Limitation of Liability under the Montreal Convention
On 18 October 2024, the International Civil Aviation Organisation (ICAO) announced the liability limits for death, injury, delays, baggage and cargo claims will increase from 28 December 2024 under th...
04.12.2024 Posted in Trade and Transport
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.