28.07.2021

Subcontractor entitled to raise set-off claim against principal’s warranty claim

A recent High Court case examined the all too common situation where a contractor goes into liquidation, but there are unresolved matters on a construction project affecting both the principal and subcontractor.  In Asphalt Supply Company Ltd v Cole John Ltd [2021] NZHC 1257 particular circumstances meant the principal was able to directly pursue the subcontractor for defective works, while the subcontractor equally could set-off amounts unpaid to it by the contractor.

Background

Cole John Ltd (CJL) engaged Complete Ltd (Complete) to undertake construction work.  In turn, Complete engaged Asphalt Supply Company Ltd (ASCO) as a subcontractor to complete certain asphalt work. 

Once ASCO had carried out its subcontracted work, Complete refused to pay the balance of the contract price (c $80K), on the basis it was payable upon ‘completion’, and because it alleged the work was defective it was not complete.  Complete promised to pay the balance upon receipt from ASCO of a six month warranty in favour of CJL.  Despite ASCO providing the warranty, Complete did not pay and promptly went into liquidation.

There was no direct contractual arrangement between ASCO and CJL, so ASCO was unable to recover the balance from CJL directly.  When CJL claimed against ASCO for a breach of the warranty and negligence in respect of the defective work, ASCO argued it was entitled to set off, against any damages in CJL’s favour, the balance left unpaid by Complete.  ASCO was unsuccessful in the District Court, and c $130K damages were awarded against it.

ASCO succeeds on appeal

On appeal, the High Court agreed that CJL was entitled to rely on the warranty, the work was indeed defective, and CJL’s loss was correctly quantified.  However, it allowed the appeal, finding the work was complete (albeit defective) and ASCO was therefore entitled to set-off the unpaid balance against CJL’s warranty claim.

The ability for ASCO to set-off the unpaid balance against the warranty claim was a result of s 18(2) of the Contract and Commercial Law Act 2017 (CCLA).  That section provides that a party in ASCO’s position has available, by way of a defence, set-off, or otherwise, any matter that would have been available to it:

  • if CJL had been a party to the contract in which the warranty was contained; or
  • if CJL was the promisee (ie Complete), the warranty had been made for the benefit of the promisee, and the proceeding had been brought against ASCO by the promisee.

Had Complete sued ASCO for the defective work, the measure of damages would have had to make an allowance for the balance of the contract price.  The normal measure of damages for incomplete or defective work under a construction contract is the cost of completing the work or remedying the defects, less any sum that would have been payable to the contractor had the work been properly carried out. Otherwise, the plaintiff would be overcompensated.

Under s 18(2) of the CCLA, the same allowance had to be made when CJL sued as the beneficiary of the warranty.  As a result, the unpaid balance was offset against CJL’s damages, which were reduced to c $50K.

Our comment 

The facts of this case will be familiar to many construction projects.  As with any project, there are a number of parties, not all of whom will have direct contractual relationships with each other.  Contractual arrangements must be carefully considered, particularly where solvency concerns arise.  Equally, the terms of any warranties and the specific wording of warranties should be carefully considered, including for whose benefit the warranty is provided.  Careful consideration, with legal input as appropriate, is required.

If you wish to discuss this case or any matters arising out of this decision or construction projects generally please contact our Construction Team or your usual contact at Hesketh Henry.

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

 

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Fern forest NZ
Bioenergy in New Zealand: Fuels for the Future?
The energy transition from combustion fuels to low carbon alternatives is viewed as critical in the race to cut global CO2 emissions and reach climate targets.  We look at some of the opportunities p...
14.11.2023 Posted in Business Advice & Climate Change & Forestry
Will Wide BW
A well drafted will is a craft
The New Zealand do-it-yourself “DIY” attitude and way of life is not limited to home improvements, but sometimes also extends to wills.  Recently we had a DIY $5.99 fill in the blanks will acros...
07.11.2023 Posted in Private Wealth
rsz large pillars
Health and Safety: The Consequences of Dishonesty
Siddhartha Gautama said that lies are like huge, gaudy vessels, the rafters of which are rotten and worm-eaten, and that those who embark in them are fated to be shipwrecked.  Two remarkable health a...
03.11.2023 Posted in Employment & Health & Safety
Properly sequencing your Construction Adjudications: Henry Construction Projects Ltd v Alu-Fix (UK) Ltd
According to the UK’s Technology and Construction Court (TCC) (in Henry Construction Projects Ltd v Alu-Fix (UK) Ltd [2023] EWHC 2010) valid payment claims must be paid before the underlying merits ...
30.10.2023 Posted in Construction & Disputes
Key change to rules on distribution of surplus assets under the new Incorporated Societies Act 2022
On 5 October 2023, the new Incorporated Societies Act 2022 (2022 Act) came fully into force, replacing the Incorporated Societies Act 1908 (1908 Act). One of the key requirements under the 2022 Act is...
18.10.2023 Posted in Business Advice
Construction Framework Wide BW
Major milestone passed – NZS3910:2023 expected in time to fill Christmas stockings
As the most widely adopted standard form construction contract in NZ, NZS 3910 was more than ready for updated conditions given the changes in the industry since its last review in 2013.  After almos...
09.10.2023 Posted in Construction
Time is money – availability provisions in employment agreements and the requirement to compensate
What happens when an availability provision is non-compliant because it does not allow for compensation, but the employee is not “required” to work additional hours?  Can the employee still be sa...
21.09.2023 Posted in Business Advice & Employment
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.