21.09.2022

Russia, Sanctions, and Force Majeure: MUR Shipping BV v RTI Ltd

It is common for force majeure clauses to define a “force majeure event” as being one that cannot reasonably be prevented by the parties. The wording may differ among clauses, but the requirement that there be no “reasonable” avoidance of the force majeure event for it to be triggered, is a frequent feature.

MUR Shipping BV v RTI Ltd [2022] EWHC 467 (Comm) clarifies that what is deemed “reasonable” in respect of overcoming / avoiding a force majeure event does not include an obligation to accept non-contractual performance or a variation to the terms of the contract.

The Decision

The case concerned a Contract of Affreightment (COA) for cargo transported between Guinea and Ukraine. The imposition of US sanctions on RTI Ltd’s (Charterers) parent company restricted its ability to pay MUR Shipping BV (Owners) in US dollars, which was the contractually specified currency for freight.

The Owners invoked the force majeure clause in the COA on the basis it could not be expected to perform without payment under the terms of the COA.

The clause excused performance only where the preventative event was outside of the affected party’s control and could not be overcome by “reasonable endeavours”.

The Charterers argued that force majeure did not apply, as the event could be reasonably overcome by accepting the Charterers’ offer to pay in Euros (including compensation for any additional costs caused by the change in currency).

The English Commercial Court held in favour of the Owners.  It found that the exercise of “reasonable endeavours” is directed at a situation in which the force majeure event can be surmounted in order for the contract to be performed.  It does not extend to varying the terms of the contract to sidestep the force majeure event.

This interpretation is equally applicable to New Zealand parties facing compliance issues because of sanctions, particularly as reliance (or attempted reliance) on force majeure clauses has become increasingly common in the current economic and political climate.   

If you have any questions about force majeure or contracts of affreightment, please get in touch with our Trade & Transport Team or your usual contact at Hesketh Henry.

 

Disclaimer:  The information contained in this article is current at the date of publishing and is of a general nature.  It should be used as a guide only and not as a substitute for obtaining legal advice.  Specific legal advice should be sought where required.

 

Do you need expert legal advice?
Contact the expert team at Hesketh Henry.
Kerry
Media contact - Kerry Browne
Please contact Kerry with any media enquiries and with any questions related to marketing or sponsorships on +64 9 375 8747 or via email.

Related Articles / Insights & Opinion

Privacy Commissioner to consult on Privacy Rules for Biometric Information
With the increasing use of facial recognition technology (FRT), retinal scans, and voice recognition by an array of different agencies, privacy concerns about its collection and use are set to be form...
24.11.2023 Posted in Business Advice
Fern forest NZ
Bioenergy in New Zealand: Fuels for the Future?
The energy transition from combustion fuels to low carbon alternatives is viewed as critical in the race to cut global CO2 emissions and reach climate targets.  We look at some of the opportunities p...
14.11.2023 Posted in Business Advice & Climate Change & Forestry
Will Wide BW
A well drafted will is a craft
The New Zealand do-it-yourself “DIY” attitude and way of life is not limited to home improvements, but sometimes also extends to wills.  Recently we had a DIY $5.99 fill in the blanks will acros...
07.11.2023 Posted in Private Wealth
rsz large pillars
Health and Safety: The Consequences of Dishonesty
Siddhartha Gautama said that lies are like huge, gaudy vessels, the rafters of which are rotten and worm-eaten, and that those who embark in them are fated to be shipwrecked.  Two remarkable health a...
03.11.2023 Posted in Employment & Health & Safety
Properly sequencing your Construction Adjudications: Henry Construction Projects Ltd v Alu-Fix (UK) Ltd
According to the UK’s Technology and Construction Court (TCC) (in Henry Construction Projects Ltd v Alu-Fix (UK) Ltd [2023] EWHC 2010) valid payment claims must be paid before the underlying merits ...
30.10.2023 Posted in Construction & Disputes
Key change to rules on distribution of surplus assets under the new Incorporated Societies Act 2022
On 5 October 2023, the new Incorporated Societies Act 2022 (2022 Act) came fully into force, replacing the Incorporated Societies Act 1908 (1908 Act). One of the key requirements under the 2022 Act is...
18.10.2023 Posted in Business Advice
Construction Framework Wide BW
Major milestone passed – NZS3910:2023 expected in time to fill Christmas stockings
As the most widely adopted standard form construction contract in NZ, NZS 3910 was more than ready for updated conditions given the changes in the industry since its last review in 2013.  After almos...
09.10.2023 Posted in Construction
SEND AN ENQUIRY
Send us an enquiry

For expert legal advice, please complete the form below or call us on (09) 375 8700.